7356-7358 N ENFIELD AVE 91335

Certificate Information: 7356-7358 N ENFIELD AVE 91335

Application / Permit
25014-20000-03337
Plan Check / Job No.
B25VN21188
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING ATTACHED GARAGE, PORTION OF SFD, AND NEW ADDITION TO NEW ACCESSORY DWELLING UNIT (843 SF) PER LAMC 12.22 A.33(c) and (e). NEW ADDITION AND REMODEL OF EXISTING SFD, NEW ATTACHED COVERED PORCH, NEW ATTACHED COVERED PATIO. ALL WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 8/14/2025
Issuing Office
Valley
Current Status
Issued on 8/14/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/23/2025 APPLICANT
Assigned to Plan Check Engineer 7/28/2025 JEROME MAGAT PALMA
Corrections Issued 7/30/2025 JEROME MAGAT PALMA
Building Plans Picked Up 7/31/2025 APPLICANT
Issued 8/14/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/1/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 8/1/2025 BIAINA HARITUNIAN
Sewer availability Cleared 8/1/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 8/5/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/24/2025 Partial Approval JUAN ALVARADO
Footing/Foundation/Slab 9/26/2025 Approved JUAN ALVARADO
Underground Mechanical 2/9/2026 Partial Approval JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 2/10/2026 Approved JUAN ALVARADO
BUILDING-Rough-Frame 4/15/2026 Approved JUAN ALVARADO
ELECTRICAL-Rough 4/15/2026 Approved JUAN ALVARADO
Green Building Rough 4/15/2026 Approved JUAN ALVARADO
HVAC-Rough 4/15/2026 Approved JUAN ALVARADO
Interior/Exterior Lathing 4/15/2026 Approved JUAN ALVARADO
PLUMBING-Rough 4/15/2026 Approved JUAN ALVARADO
Underground Mechanical 4/15/2026 Approved JUAN ALVARADO
Insulation 6/18/2026 Corrections Issued JUAN ALVARADO
Interior/Exterior Lathing 6/29/2026 Not Ready for Inspection JUAN ALVARADO
Shower Pan 6/29/2026 Approved JUAN ALVARADO
Drywall Nailing 7/17/2026 Approved JUAN ALVARADO
Insulation 7/17/2026 Approved JUAN ALVARADO
Interior/Exterior Lathing 7/17/2026 Approved JUAN ALVARADO