10646 N HADDON AVE 91331

Certificate Information: 10646 N HADDON AVE 91331

Application / Permit
25014-20000-03328
Plan Check / Job No.
B25VN21154
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE AND (N) ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1)3 ALL WORK PER ENGINNERING
Permit Issued
Issued on 4/7/2026
Issuing Office
Current Status
Issued on 4/7/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/23/2025 APPLICANT
Assigned to Plan Check Engineer 7/28/2025 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 7/30/2025 SEWADA ZADOORIAN MILAGARDI
Building Plans Picked Up 7/30/2025 APPLICANT
Issued 4/7/2026 APPLICANT

Permit Application Clearance Information

ZI Cleared 8/4/2025 DAVID URITA
Address approval Cleared 8/7/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 8/7/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 8/13/2025 BIAINA HARITUNIAN
Sewer availability Cleared 4/6/2026 JEFF LOREDO

Contact Information

Contractor Vision Adu Llc; Lic. No.: 1115842-B 1440 6HS STATE COLLEGE BLVD      ANAHEIM, CA 92806
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Barrier 5/19/2026 Approved MICHEL ABAJAN
METHANE-Subgrade 5/19/2026 Approved MICHEL ABAJAN
PLUMBING-Rough 5/19/2026 Partial Approval MICHEL ABAJAN
Sewer 5/19/2026 Not Ready for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 5/26/2026 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 6/16/2026 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 6/16/2026 Corrections Issued MATTHEW NELSON
Green Building Rough 6/16/2026 Approved MATTHEW NELSON
HVAC-Rough 6/16/2026 Approved MATTHEW NELSON
METHANE-Rough 6/16/2026 Approved MATTHEW NELSON
PLUMBING-Rough 6/16/2026 Corrections Issued MATTHEW NELSON
Wood Frame 6/16/2026 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 6/22/2026 Approved MICHEL ABAJAN
ELECTRICAL-Rough 6/22/2026 Approved MICHEL ABAJAN
Interior/Exterior Lathing 6/22/2026 Approved MICHEL ABAJAN
PLUMBING-Rough 6/22/2026 Approved MICHEL ABAJAN
Insulation 6/29/2026 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 7/6/2026 Partial Approval MICHEL ABAJAN
Drywall Nailing 7/9/2026 Approved MICHEL ABAJAN
Interior/Exterior Lathing 7/9/2026 Approved MICHEL ABAJAN