11471 W SUNSET BLVD 90049
Certificate Information: 11471 W SUNSET BLVD 90049
- Application / Permit
- 25014-20000-03309
- Plan Check / Job No.
- B25VN20972
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2502 SQ FT ADDITION AND REMODEL TO (E) SINGLE FAMILY DWELLING; CONVERT ATTACHED GARAGE TO PART OF SFD; ADD (N) 563 SQ FT GARAGE
- Permit Issued
- Issued on 10/29/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 10/29/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2025 | SELLA BENYAMIN |
| Corrections Issued | 8/14/2025 | SELLA BENYAMIN |
| Quality Review Completed | 8/15/2025 | STEVEN KIM |
| Building Plans Picked Up | 8/20/2025 | APPLICANT |
| Plan Check Approved | 10/7/2025 | SELLA BENYAMIN |
| Issued | 10/29/2025 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/25/2025 | KIMBERLY HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 8/25/2025 | KIMBERLY HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 8/25/2025 | KIMBERLY HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 8/25/2025 | KIMBERLY HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2025 | KIMBERLY HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 9/15/2025 | KIMBERLY HERNANDEZ |
| Sewer availability | Cleared | 9/15/2025 | KIMBERLY HERNANDEZ |
| GPI Written Notices | Cleared | 10/7/2025 | SELLA BENYAMIN |
| Grading Pre-Inspection | Cleared | 10/7/2025 | SELLA BENYAMIN |
Contact Information
| Architect | Miller,, Michael; Lic. No.: C26956 | 12756 MITCHELL AVE LOS ANGELES, CA 90066 |
| Contractor | Foundation To Roof Inc; Lic. No.: 767761-B | 27058 ESWARD DR AGOURA HILLS, CA 91301 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 1/9/2026 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 1/9/2026 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 1/9/2026 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 1/9/2026 | Corrections Issued | EVAN COOPER |
| Shower Pan | 1/9/2026 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 1/21/2026 | Corrections Issued | EVAN COOPER |
| Green Building Rough | 1/21/2026 | Partial Approval | EVAN COOPER |
| Interior/Exterior Lathing | 1/21/2026 | Partial Approval | EVAN COOPER |
| MERV13>=Rough | 1/21/2026 | Approved | EVAN COOPER |
| PLUMBING-Rough | 1/21/2026 | Partial Approval | EVAN COOPER |
| Insulation | 1/28/2026 | Partial Approval | EVAN COOPER |
| Interior/Exterior Lathing | 1/28/2026 | Partial Approval | EVAN COOPER |
| Drywall Nailing | 2/17/2026 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 3/13/2026 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 3/18/2026 | Corrections Issued | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 3/20/2026 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 4/21/2026 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 5/13/2026 | Partial Approval | CARLOS MATAMOROS |