10824 N SPRINGFIELD AVE 91326

Certificate Information: 10824 N SPRINGFIELD AVE 91326

Application / Permit
25014-20000-03272
Plan Check / Job No.
B25VN20652
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan REMOVE ONE (E) PATIO COVER AND CONVERT OTHER EXISTING PATIO COVER TO MAKE PART OF (E) 2-STORY SFD WITH ATTACHED GARAGE. GROUND FLOOR AND 2ND FLOOR ADDITION AND REMODEL.
Permit Issued
Issued on 12/19/2025
Issuing Office
Current Status
Issued on 12/19/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/18/2025 APPLICANT
Assigned to Plan Check Engineer 8/7/2025 ADRIANA LOPEZ
Corrections Issued 8/21/2025 ADRIANA LOPEZ
Quality Review Completed 9/8/2025 HERNAN ARREOLA
Applicant returned to address corrections 9/23/2025 ADRIANA LOPEZ
Applicant returned to address corrections 10/27/2025 ADRIANA LOPEZ
Applicant returned to address corrections 12/9/2025 ADRIANA LOPEZ
Plan Check Approved 12/19/2025 ADRIANA LOPEZ
Issued 12/19/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/5/2025 SAFA JAVANMARDI
Sewer availability Cleared 9/5/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 9/11/2025 SAFA JAVANMARDI
GPI Written Notices Cleared 12/19/2025 ADRIANA LOPEZ
Grading Pre-Inspection Cleared 12/19/2025 ADRIANA LOPEZ

Contact Information

Contractor Sunset Home Builders Inc; Lic. No.: 1094054-B       ,
Engineer Mniarji,, Majd Sameer; Lic. No.: C93049 7812 VASSAR AVENUE      CANOGA PARK, CA 91304

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Interior/Exterior Lathing 6/8/2026   

Inspection Request History

PLUMBING-Rough 1/14/2026 Partial Approval DAVID SCANTLIN
Footing/Foundation/Slab 1/23/2026 Approved KRISTEN CAUSEY
Deputy Reinf. Concrete 2/3/2026 Conditional Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 3/18/2026 Partial Approval DAVID SCANTLIN
ELECTRICAL-Rough 4/7/2026 Approved DAVID SCANTLIN
HVAC-Rough 4/7/2026 Corrections Issued DAVID SCANTLIN
PLUMBING-Rough 4/7/2026 Corrections Issued DAVID SCANTLIN
BUILDING-Rough-Frame 5/12/2026 Corrections Issued JACK KARGODORIAN
Green Building Rough 5/12/2026 Approved JACK KARGODORIAN
HVAC-Rough 5/12/2026 Corrections Issued JACK KARGODORIAN
PLUMBING-Rough 5/12/2026 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 5/14/2026 Approved JACK KARGODORIAN
Insulation 5/20/2026 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 5/20/2026 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 6/1/2026 Approved CHRISTOPHER WILSON
Shower Pan 6/1/2026 Approved CHRISTOPHER WILSON
Underground Mechanical 6/1/2026 Approved CHRISTOPHER WILSON