649 W 42ND PL 90037
Certificate Information: 649 W 42ND PL 90037
- Application / Permit
- 25014-20000-03244
- Plan Check / Job No.
- B25VN20500
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERSION AND ADDITION OF EXISTING GARAGE TO ADU PER STATE LAW.
- Permit Issued
- Issued on 10/15/2025
- Issuing Office
- Current Status
- Issued on 10/15/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2025 | EDWIN MARTINEZ |
| Corrections Issued | 7/25/2025 | EDWIN MARTINEZ |
| Applicant returned to address corrections | 10/1/2025 | DANIEL SMILEY |
| Plan Check Approved | 10/15/2025 | RICARDO RAMIREZ |
| Issued | 10/15/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/11/2025 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 9/11/2025 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2025 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 9/16/2025 | ADRIAN SANCHEZ |
| Construction near power lines | Cleared | 9/22/2025 | RIDWAN HARDY |
Contact Information
| Architect | Gross,, Robert Charles; Lic. No.: NA30389 | , |
| Contractor | Pacific West Home Builders Inc; Lic. No.: 1111181-B | , |
| Engineer | Ding,, Wenzhuo; Lic. No.: C82891 | 5205 SUNNY POINT PL RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Wood Frame | 6/9/2026 |
Inspection Request History
| Underground Mechanical | 12/5/2025 | Approved | MICHAEL LEWIS |
| Deputy Drilled-In Anchors | 12/23/2025 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 12/23/2025 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 1/15/2026 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2026 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 2/13/2026 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 3/5/2026 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2026 | Partial Approval | LUIS CASTRO |
| ELECTRICAL-Rough | 5/26/2026 | Not Ready for Inspection | WILLIAM SIERRA |
| HVAC-Rough | 5/26/2026 | Not Ready for Inspection | WILLIAM SIERRA |
| Wood Frame | 5/26/2026 | Not Ready for Inspection | WILLIAM SIERRA |
| ELECTRICAL-Rough | 6/3/2026 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 6/3/2026 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 6/5/2026 | No Result Entered | SABAS ALONSO |
| HVAC-Rough | 6/5/2026 | No Result Entered | SABAS ALONSO |
| Wood Frame | 6/5/2026 | No Result Entered | SABAS ALONSO |