9436 N BURNET AVE 91343

Certificate Information: 9436 N BURNET AVE 91343

Application / Permit
25014-20000-03241
Plan Check / Job No.
B25VN20484
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
IRR. SHAPED ADDITION TO AND CONVERT DETACHED STORAGE ROOM TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 8/12/2025
Issuing Office
Current Status
Issued on 8/12/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/17/2025 APPLICANT
Assigned to Plan Check Engineer 7/24/2025 JEROME MAGAT PALMA
Corrections Issued 7/25/2025 JEROME MAGAT PALMA
Building Plans Picked Up 7/28/2025 APPLICANT
Plan Check Approved 8/12/2025 ANGELICA MARTINEZ
Issued 8/12/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/31/2025 DERRICK MAGEE
Roof/Waste drainage to street Cleared 7/31/2025 DERRICK MAGEE
Sewer availability Cleared 7/31/2025 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 8/12/2025 ROSE MARIE SMITH

Contact Information

Contractor Quality Retro Construction; Lic. No.: 1033863-B 9557 NOBLE AVE      NORTH HILLS, CA 91343

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/21/2025 Corrections Issued OGANES TARAKHCHYAN
Sewer 8/21/2025 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Rough 8/26/2025 Partial Approval VINCENT HANLEY
Sewer 8/26/2025 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 9/3/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 10/9/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/9/2025 Partial Approval VINCENT HANLEY
PLUMBING-Rough 10/9/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 10/9/2025 SGSOV Not Ready VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/14/2025 Approved DAVID ANDERSON
Gas Test 10/14/2025 Not Ready for Inspection DAVID ANDERSON
Shower Pan 10/14/2025 Not Ready for Inspection DAVID ANDERSON
Wood Frame 10/14/2025 Approved DAVID ANDERSON
Gas Test 10/16/2025 Approved MATTHEW NELSON
Insulation 10/16/2025 Not Ready for Inspection MATTHEW NELSON
Wood Frame 10/16/2025 Corrections Issued MATTHEW NELSON
HVAC-Rough 10/20/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 10/20/2025 Partial Approval DAVID ANDERSON
Underground Mechanical 10/20/2025 Partial Approval DAVID ANDERSON
Insulation 10/21/2025 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 10/27/2025 Approved VINCENT HANLEY
Drywall Nailing 10/27/2025 Approved VINCENT HANLEY
Green Building Rough 10/27/2025 Approved VINCENT HANLEY
Insulation 10/27/2025 Approved VINCENT HANLEY
Sewer 1/7/2026 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Final 1/27/2026 Approved VINCENT HANLEY
Final 1/27/2026 Corrections Issued VINCENT HANLEY
Green Building Final 1/27/2026 Approved VINCENT HANLEY
HVAC-Final 1/27/2026 Approved VINCENT HANLEY
PLUMBING-Final 1/27/2026 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 1/27/2026 SGSOV Approved VINCENT HANLEY
Smoke Detectors 1/27/2026 Approved VINCENT HANLEY