9436 N BURNET AVE 91343
Certificate Information: 9436 N BURNET AVE 91343
- Application / Permit
- 25014-20000-03241
- Plan Check / Job No.
- B25VN20484
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- IRR. SHAPED ADDITION TO AND CONVERT DETACHED STORAGE ROOM TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 8/12/2025
- Issuing Office
- Current Status
- Issued on 8/12/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 7/25/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 7/28/2025 | APPLICANT |
| Plan Check Approved | 8/12/2025 | ANGELICA MARTINEZ |
| Issued | 8/12/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/31/2025 | DERRICK MAGEE |
| Roof/Waste drainage to street | Cleared | 7/31/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 7/31/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2025 | ROSE MARIE SMITH |
Contact Information
| Contractor | Quality Retro Construction; Lic. No.: 1033863-B | 9557 NOBLE AVE NORTH HILLS, CA 91343 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/21/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| Sewer | 8/21/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 8/26/2025 | Partial Approval | VINCENT HANLEY |
| Sewer | 8/26/2025 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 9/3/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 10/9/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2025 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 10/9/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 10/9/2025 | SGSOV Not Ready | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2025 | Approved | DAVID ANDERSON |
| Gas Test | 10/14/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Shower Pan | 10/14/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Wood Frame | 10/14/2025 | Approved | DAVID ANDERSON |
| Gas Test | 10/16/2025 | Approved | MATTHEW NELSON |
| Insulation | 10/16/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Wood Frame | 10/16/2025 | Corrections Issued | MATTHEW NELSON |
| HVAC-Rough | 10/20/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 10/20/2025 | Partial Approval | DAVID ANDERSON |
| Underground Mechanical | 10/20/2025 | Partial Approval | DAVID ANDERSON |
| Insulation | 10/21/2025 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/27/2025 | Approved | VINCENT HANLEY |
| Drywall Nailing | 10/27/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 10/27/2025 | Approved | VINCENT HANLEY |
| Insulation | 10/27/2025 | Approved | VINCENT HANLEY |
| Sewer | 1/7/2026 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 1/27/2026 | Approved | VINCENT HANLEY |
| Final | 1/27/2026 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 1/27/2026 | Approved | VINCENT HANLEY |
| HVAC-Final | 1/27/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 1/27/2026 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 1/27/2026 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 1/27/2026 | Approved | VINCENT HANLEY |