5736 N BECK AVE 91601

Certificate Information: 5736 N BECK AVE 91601

Application / Permit
25014-20000-03240
Plan Check / Job No.
B25VN20478
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
[ePlan] (E) garage conversion to ADU with addition Single story. per LAMC 12.22 A.33 (c) and (e).
Permit Issued
Issued on 11/20/2025
Issuing Office
Current Status
Issued on 11/20/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/21/2025 APPLICANT
Assigned to Plan Check Engineer 7/24/2025 ZENA HADDIS
Corrections Issued 8/27/2025 ZENA HADDIS
Quality Review Completed 9/4/2025 CHIHARU SUZUKI
Plan Check Approved 11/19/2025 ZENA HADDIS
Issued 11/20/2025 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 10/7/2025 WALTER RAMIREZ
Hydrant and Access approval Cleared 10/9/2025 LAVEON RIDER
Address approval Cleared 10/20/2025 ROSE STEIN-WENDT
Roof/Waste drainage to street Cleared 10/20/2025 ROSE STEIN-WENDT
Eng Process Fee Ord 176,300 Cleared 10/21/2025 ROSE STEIN-WENDT
Sewer availability Cleared 10/21/2025 ROSE STEIN-WENDT

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: NA76761       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/2/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 12/4/2025 Partial Approval JAVIER RAMOS JR
Underground Mechanical 12/4/2025 Partial Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 12/10/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 12/10/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/22/2025 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 1/30/2026 Approved JAVIER RAMOS JR
HVAC-Rough 1/30/2026 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 1/30/2026 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 1/30/2026 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 3/9/2026 Approved JAVIER RAMOS JR
Green Building Rough 3/9/2026 Approved JAVIER RAMOS JR
Insulation 3/9/2026 Approved JAVIER RAMOS JR
Drywall Nailing 3/16/2026 Approved JAVIER RAMOS JR
Sewer 3/16/2026 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 4/8/2026 Approved RAUL OLAGI
Shower Pan 4/8/2026 Approved RAUL OLAGI
ELECTRICAL-Final 4/29/2026 Approved JAVIER RAMOS JR
Gas Test 4/29/2026 Approved JAVIER RAMOS JR
Service/Power Release 4/29/2026 Approved JAVIER RAMOS JR
Smoke Detectors 4/29/2026 Approved JAVIER RAMOS JR
Final 5/5/2026 Corrections Issued JAVIER RAMOS JR
Green Building Final 5/5/2026 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 5/5/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 5/5/2026 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/5/2026 SGSOV Approved JAVIER RAMOS JR
Final 5/14/2026 Corrections Issued JAVIER RAMOS JR
Green Building Final 5/14/2026 Approved JAVIER RAMOS JR
Final 5/29/2026 Not Ready for Inspection GAREN HAYRAPETYAN