5738-5740 N BECK AVE 91601
Certificate Information: 5738-5740 N BECK AVE 91601
- Application / Permit
- 25014-20000-03221
- Plan Check / Job No.
- B25VN20364
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- PROPOSED 452 SF ONE STORY ADDITION AND MAJOR REMODEL TO EXISTING DUPLEX _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
- Permit Issued
- Issued on 10/3/2025
- Issuing Office
- Current Status
- CofO Issued on 7/1/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2025 | DAWN MC NULTY |
| Corrections Issued | 7/21/2025 | DAWN MC NULTY |
| Quality Review Completed | 7/24/2025 | OMID HEDAYAT |
| Applicant returned to address corrections | 8/22/2025 | DAWN MC NULTY |
| Applicant returned to address corrections | 9/15/2025 | DAWN MC NULTY |
| Plan Check Approved | 9/29/2025 | DAWN MC NULTY |
| Issued | 10/3/2025 | APPLICANT |
| CofO in Progress | 5/15/2026 | JAVIER RAMOS JR |
| Permit Finaled | 7/1/2026 | RUBEN SALAS |
| CofO Issued | 7/1/2026 | RUBEN SALAS |
| Permit Finaled | 7/1/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/1/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/1/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 8/1/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2025 | LEE GUILBEAUX |
| APC | Cleared | 8/27/2025 | JAZMIN ROQUE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: NA76761 | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/10/2025 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 10/15/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2025 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2025 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 12/4/2025 | Partial Approval | JAVIER RAMOS JR |
| Deputy Wood Construction | 12/4/2025 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 12/4/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 12/4/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 12/4/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 12/12/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 12/12/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 12/12/2025 | Partial Approval | JAVIER RAMOS JR |
| Drywall Nailing | 12/22/2025 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 12/22/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 1/21/2026 | Approved | JAVIER RAMOS JR |
| Gas Test | 3/16/2026 | Approved | JAVIER RAMOS JR |
| Sewer | 3/16/2026 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 3/23/2026 | No Access for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Final | 4/13/2026 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 4/13/2026 | Approved | JAVIER RAMOS JR |
| Final | 5/5/2026 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 5/5/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 5/5/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 5/5/2026 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 5/5/2026 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 5/5/2026 | Partial Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 5/5/2026 | Approved | JAVIER RAMOS JR |
| Final | 5/14/2026 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 5/14/2026 | Approved | JAVIER RAMOS JR |