8145 N MORSE AVE 91605

Certificate Information: 8145 N MORSE AVE 91605

Application / Permit
25014-20000-03209
Plan Check / Job No.
B25VN20281
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Supplemental permit to 24014-20000-04771 to revise the scope of work from adu conversion to new adu construction PER LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k)
Permit Issued
Issued on 8/28/2025
Issuing Office
Current Status
CofO Issued on 12/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2025 APPLICANT
Assigned to Plan Check Engineer 7/18/2025 NGHI SU
Corrections Issued 7/20/2025 NGHI SU
Plan Check Approved 7/29/2025 NGHI SU
Issued 8/28/2025 APPLICANT
CofO in Progress 11/19/2025 JAVIER RAMOS JR
Permit Finaled 12/19/2025 RUBEN SALAS
CofO Issued 12/19/2025 RUBEN SALAS
Permit Finaled 12/19/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/25/2025 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/25/2025 JEANIE LAM
Roof/Waste drainage to street Cleared 7/25/2025 JEANIE LAM
Sewer availability Cleared 7/25/2025 JEANIE LAM

Contact Information

Architect Sabet,, Golnarges M; Lic. No.: C33474 3621 S. BENTLEY AVENUE      LOS ANGELES, CA 90034
Architect Sabet,, Golnarges M; Lic. No.: NA33474       ,
Contractor Golnarges Sabet; Lic. No.: 1075932-B       ,
Contractor Sabet Golnarges; Lic. No.: 1075932-B       ,
Engineer Sivushenka,, Mikita; Lic. No.: NA87698       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/5/2025 Partial Approval VINCENT HANLEY
Sewer 9/5/2025 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 9/8/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 9/8/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 9/15/2025 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/15/2025 Approved VINCENT HANLEY
Green Building Rough 9/15/2025 Not Ready for Inspection VINCENT HANLEY
Wood Frame 9/15/2025 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 9/22/2025 Approved VINCENT HANLEY
ELECTRICAL-Rough 9/22/2025 Approved VINCENT HANLEY
Green Building Rough 9/22/2025 Approved VINCENT HANLEY
HVAC-Rough 9/22/2025 Approved VINCENT HANLEY
PLUMBING-Rough 9/22/2025 Approved VINCENT HANLEY
Shower Pan 9/22/2025 Approved VINCENT HANLEY
Insulation 9/24/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 9/24/2025 Partial Approval VINCENT HANLEY
Drywall Nailing 9/29/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 9/29/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 11/12/2025 Approved JAVIER RAMOS JR
Final 11/12/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 11/12/2025 Approved JAVIER RAMOS JR
HVAC-Final 11/12/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 11/12/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 11/12/2025 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 11/12/2025 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 11/12/2025 Approved JAVIER RAMOS JR
Final 11/19/2025 OK to Issue CofO JAVIER RAMOS JR
Service/Power Release 11/19/2025 Partial Inspection JAVIER RAMOS JR