20219 W BASSETT ST 91306

Certificate Information: 20219 W BASSETT ST 91306

Application / Permit
25014-20000-03208
Plan Check / Job No.
B25VN20278
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT EXISTING DETACHED GARAGE TO ADU WITH ADDITION PER GCS66323(a)(2), ALL WORK PER ENG.
Permit Issued
Issued on 9/22/2025
Issuing Office
Current Status
Issued on 9/22/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/16/2025 APPLICANT
Assigned to Plan Check Engineer 7/18/2025 LUISANGEL VALENZUELA
Corrections Issued 7/19/2025 LUISANGEL VALENZUELA
Plan Check Approved 9/12/2025 LUISANGEL VALENZUELA
Issued 9/22/2025 APPLICANT

Permit Application Clearance Information

ZI Cleared 7/23/2025 BRENNEN OBETO
Address approval Cleared 7/24/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 7/24/2025 SAFA JAVANMARDI
Sewer availability Cleared 8/1/2025 SAFA JAVANMARDI
Construction near power lines Cleared 8/29/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Tangonan,, Jeffrey Tolentino; Lic. No.: C83522 17770 CAPE JASMINE RD      CANYON COUNTRY, CA 91387

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Green Building Final 7/30/2026   
Final 7/30/2026   

Inspection Request History

Pre-Inspection 10/16/2025 Partial Inspection ALEXANDER HANDY
PLUMBING-Rough 10/27/2025 Corrections Issued SCOTT SOBEL
PLUMBING-Rough 10/30/2025 Partial Approval ALEXANDER HANDY
Deputy Drilled-In Anchors 11/6/2025 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 11/10/2025 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 12/12/2025 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Rough 12/12/2025 Approved ALEXANDER HANDY
HVAC-Rough 12/12/2025 Conditional Approval ALEXANDER HANDY
PLUMBING-Rough 12/12/2025 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Rough 12/18/2025 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 12/26/2025 Corrections Issued JON MCHUGH
Interior/Exterior Lathing 12/26/2025 No Access for Inspection JON MCHUGH
Insulation 1/2/2026 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 1/29/2026 Approved MORRIS JACKSON
Drywall Nailing 1/29/2026 Approved MORRIS JACKSON
Green Building Rough 1/29/2026 Approved MORRIS JACKSON
Shower Pan 2/18/2026 Approved DAVID FASTIGGI
Interior/Exterior Lathing 4/10/2026 Approved DAVID FASTIGGI
Underground Mechanical 4/10/2026 Approved DAVID FASTIGGI
Final 7/17/2026 Corrections Issued ROBERT GOLD
Footing/Foundation/Slab 7/17/2026 Approved ROBERT GOLD
Green Building Final 7/17/2026 Not Ready for Inspection ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 7/17/2026 SGSOV Not Ready ROBERT GOLD
Smoke Detectors 7/17/2026 Approved ROBERT GOLD
Final 7/23/2026 Corrections Issued ALEXANDER HANDY
Green Building Final 7/23/2026 Not Ready for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 7/23/2026 SGSOV Approved ALEXANDER HANDY