4538-4540 N MORSE AVE 91604
Certificate Information: 4538-4540 N MORSE AVE 91604
- Application / Permit
- 25014-20000-03137
- Plan Check / Job No.
- B25VN19837
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- MAJOR REMODEL TO KEEP (E) 3'-6" WALL/FOOTING WITH ADDITIONS TO CREATE A 2-STORY SINGLE FAMILY DWELLING UNIT WITH 2ND FLOOR BALCONY, ATTACHED 2-CAR GARAGE, AND ATTACHED ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c) and (e) PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
- Permit Issued
- Issued on 9/29/2025
- Issuing Office
- Current Status
- Issued on 9/29/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2025 | ALFRED RAMIREZ |
| Corrections Issued | 7/30/2025 | ALFRED RAMIREZ |
| Quality Review Completed | 8/1/2025 | STEVEN KIM |
| Building Plans Picked Up | 8/5/2025 | APPLICANT |
| Applicant returned to address corrections | 9/25/2025 | ALFRED RAMIREZ |
| Plan Check Approved | 9/29/2025 | ALFRED RAMIREZ |
| Issued | 9/29/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/8/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 8/11/2025 | SAFA JAVANMARDI |
| Low Impact Development (LID) | Cleared | 9/4/2025 | ERNEST TSE |
| Trees in Parkway | Cleared | 9/8/2025 | RICHARD SANCHEZ |
| Permit | Cleared | 9/10/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 9/10/2025 | SAFA JAVANMARDI |
| ZI | Cleared | 9/25/2025 | DANIEL CORONADO |
Contact Information
| Contractor | Mlr Development Corporation; Lic. No.: 1027283-B | 15720 VENTURA BLVD SUITE 405 ENCINO, CA 91436 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| PLUMBING-Final | 7/23/2026 Time Frame: 9-11 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/17/2025 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 10/17/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 10/17/2025 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 10/22/2025 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/5/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 11/5/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Wood Frame | 11/5/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/13/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 11/13/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 12/11/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 12/22/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Rough | 12/22/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Pre-Inspection | 12/22/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 1/5/2026 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Rough | 1/5/2026 | Corrections Issued | CHRISTOPHE COCHRAN |
| Shower Pan | 1/5/2026 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 1/7/2026 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 1/7/2026 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 1/8/2026 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Drilled-In Anchors | 1/8/2026 | Conditional Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 1/8/2026 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 1/8/2026 | Partial Approval | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 1/12/2026 | Partial Approval | JACK KARGODORIAN |
| Interior/Exterior Lathing | 1/23/2026 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 1/27/2026 | Corrections Issued | CHRISTOPHE COCHRAN |
| Wood Frame | 1/27/2026 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Insulation | 2/3/2026 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 2/3/2026 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 2/6/2026 | Approved | CHRISTOPHE COCHRAN |
| Masonry Wall/Backfill | 4/21/2026 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 7/16/2026 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 7/16/2026 | Approved | JAVIER RAMOS JR |