4538-4540 N MORSE AVE 91604

Certificate Information: 4538-4540 N MORSE AVE 91604

Application / Permit
25014-20000-03137
Plan Check / Job No.
B25VN19837
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
MAJOR REMODEL TO KEEP (E) 3'-6" WALL/FOOTING WITH ADDITIONS TO CREATE A 2-STORY SINGLE FAMILY DWELLING UNIT WITH 2ND FLOOR BALCONY, ATTACHED 2-CAR GARAGE, AND ATTACHED ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c) and (e) PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
Permit Issued
Issued on 9/29/2025
Issuing Office
Current Status
Issued on 9/29/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/11/2025 APPLICANT
Assigned to Plan Check Engineer 7/24/2025 ALFRED RAMIREZ
Corrections Issued 7/30/2025 ALFRED RAMIREZ
Quality Review Completed 8/1/2025 STEVEN KIM
Building Plans Picked Up 8/5/2025 APPLICANT
Applicant returned to address corrections 9/25/2025 ALFRED RAMIREZ
Plan Check Approved 9/29/2025 ALFRED RAMIREZ
Issued 9/29/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/8/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 8/11/2025 SAFA JAVANMARDI
Sewer availability Cleared 8/11/2025 SAFA JAVANMARDI
Low Impact Development (LID) Cleared 9/4/2025 ERNEST TSE
Trees in Parkway Cleared 9/8/2025 RICHARD SANCHEZ
Permit Cleared 9/10/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 9/10/2025 SAFA JAVANMARDI
ZI Cleared 9/25/2025 DANIEL CORONADO

Contact Information

Contractor Mlr Development Corporation; Lic. No.: 1027283-B 15720 VENTURA BLVD SUITE 405      ENCINO, CA 91436
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

PLUMBING-Final 7/23/2026    Time Frame: 9-11

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/17/2025 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 10/17/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 10/17/2025 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 10/22/2025 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 11/5/2025 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 11/5/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Wood Frame 11/5/2025 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 11/13/2025 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 11/13/2025 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 11/13/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 12/11/2025 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 12/22/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 12/22/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Pre-Inspection 12/22/2025 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Rough 1/5/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 1/5/2026 Corrections Issued CHRISTOPHE COCHRAN
Shower Pan 1/5/2026 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 1/7/2026 Approved CHRISTOPHE COCHRAN
HVAC-Rough 1/7/2026 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 1/8/2026 Partial Approval CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 1/8/2026 Conditional Approval JOAQUIN GREENOUGH
Green Building Rough 1/8/2026 Approved CHRISTOPHE COCHRAN
Wood Frame 1/8/2026 Partial Approval CHRISTOPHE COCHRAN
Interior/Exterior Lathing 1/12/2026 Partial Approval JACK KARGODORIAN
Interior/Exterior Lathing 1/23/2026 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 1/27/2026 Corrections Issued CHRISTOPHE COCHRAN
Wood Frame 1/27/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
Insulation 2/3/2026 Approved CHRISTOPHE COCHRAN
Wood Frame 2/3/2026 Approved CHRISTOPHE COCHRAN
Drywall Nailing 2/6/2026 Approved CHRISTOPHE COCHRAN
Masonry Wall/Backfill 4/21/2026 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 7/16/2026 Approved JAVIER RAMOS JR
Service/Power Release 7/16/2026 Approved JAVIER RAMOS JR