647 N STANLEY AVE 90036
Certificate Information: 647 N STANLEY AVE 90036
- Application / Permit
- 25014-20000-03134
- Plan Check / Job No.
- B25VN19828
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 34'-8" X 65'-7" AND 12'-7" X 3' TO EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 8/29/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2025 | SELLA BENYAMIN |
| Corrections Issued | 7/22/2025 | SELLA BENYAMIN |
| Quality Review Completed | 7/24/2025 | STEVEN KIM |
| Building Plans Picked Up | 7/28/2025 | APPLICANT |
| Plan Check Approved | 8/28/2025 | SELLA BENYAMIN |
| Issued | 8/29/2025 | APPLICANT |
| CofO in Progress | 5/14/2026 | JOSH MEISTER |
| Permit Finaled | 5/15/2026 | DEROLD HAUFF |
| CofO Issued | 5/15/2026 | DEROLD HAUFF |
| Permit Finaled | 5/15/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2025 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 8/19/2025 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 8/19/2025 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/10/2025 | Partial Approval | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 9/15/2025 | Corrections Issued | JOSE MACIAS |
| Excavation/Setback/Form/Re-Bar | 9/17/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Footing/Foundation/Slab | 9/17/2025 | Corrections Issued | JEFFREY MEAD |
| METHANE-Barrier | 9/17/2025 | Not Ready for Inspection | JEFFREY MEAD |
| METHANE-Subgrade | 9/17/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 9/18/2025 | Partial Approval | JOSE MACIAS |
| METHANE-Subgrade | 9/23/2025 | Approved | RONNIE MINDANAO |
| METHANE-Barrier | 11/4/2025 | Approved | JOSH MEISTER |
| METHANE-Rough | 11/4/2025 | Approved | JOSH MEISTER |
| Footing/Foundation/Slab | 11/5/2025 | Approved | JEFFREY MEAD |
| Deputy Drilled-In Anchors | 11/6/2025 | Conditional Approval | ALEX COLIN |
| BUILDING-Rough-Frame | 12/3/2025 | Not Ready for Inspection | JOSH MEISTER |
| Green Building Rough | 12/3/2025 | Not Ready for Inspection | JOSH MEISTER |
| Reinforced Concrete Frame | 12/3/2025 | Not Ready for Inspection | JOSH MEISTER |
| Wood Frame | 12/3/2025 | Not Ready for Inspection | JOSH MEISTER |
| Light Gage Steel Frame | 12/9/2025 | Not Ready for Inspection | JOSH MEISTER |
| Reinforced Concrete Frame | 12/9/2025 | Not Ready for Inspection | JOSH MEISTER |
| Reinforced Masonry Frame | 12/9/2025 | Not Ready for Inspection | JOSH MEISTER |
| Structural Steel Frame | 12/9/2025 | Not Ready for Inspection | JOSH MEISTER |
| Wood Frame | 12/9/2025 | Not Ready for Inspection | JOSH MEISTER |
| ELECTRICAL-Rough | 12/12/2025 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/12/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Sewer | 12/12/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/16/2025 | Approved | JOSH MEISTER |
| Pre-Inspection | 12/16/2025 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Rough | 12/22/2025 | Corrections Issued | JOSH MEISTER |
| HVAC-Rough | 12/29/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 12/29/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Sewer | 12/29/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| PLUMBING-Rough | 12/30/2025 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 12/31/2025 | Not Ready for Inspection | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2025 | Conditional Approval | JOSH MEISTER |
| Green Building Rough | 12/31/2025 | Not Ready for Inspection | JOSH MEISTER |
| BUILDING-Rough-Frame | 1/9/2026 | Approved | JOSH MEISTER |
| Green Building Rough | 1/9/2026 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 1/9/2026 | Partial Approval | JOSH MEISTER |
| Insulation | 1/13/2026 | Approved | ENRIQUE MIRELES |
| Shower Pan | 1/15/2026 | Approved | JOSH MEISTER |
| Drywall Nailing | 1/20/2026 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 1/20/2026 | Approved | JOSH MEISTER |
| Drywall Nailing | 1/21/2026 | Approved | JOSH MEISTER |
| HVAC-Final | 2/25/2026 | Corrections Issued | JOSH MEISTER |
| ELECTRICAL-Final | 4/30/2026 | Approved | JOSH MEISTER |
| Enclosure/Fence | 4/30/2026 | Not Ready for Inspection | JOSH MEISTER |
| Final | 4/30/2026 | Corrections Issued | JOSH MEISTER |
| Gas Test | 4/30/2026 | Corrections Issued | JOSH MEISTER |
| Green Building Final | 4/30/2026 | Corrections Issued | JOSH MEISTER |
| HVAC-Final | 4/30/2026 | Approved | JOSH MEISTER |
| METHANE-Final | 4/30/2026 | Approved | JOSH MEISTER |
| PLUMBING-Final | 4/30/2026 | Approved | JOSH MEISTER |
| Service/Power Release | 4/30/2026 | Not Ready for Inspection | JOSH MEISTER |
| Smoke Detectors | 4/30/2026 | Approved | JOSH MEISTER |
| Final | 5/4/2026 | Not Ready for Inspection | JOSH MEISTER |
| Gas Test | 5/4/2026 | Approved | JOSH MEISTER |
| Green Building Final | 5/4/2026 | Not Ready for Inspection | JOSH MEISTER |
| PLUMBING-Final | 5/4/2026 | Approved | JOSH MEISTER |
| Final | 5/6/2026 | Not Ready for Inspection | JOSH MEISTER |
| Green Building Final | 5/6/2026 | Not Ready for Inspection | JOSH MEISTER |
| SGSOV-Seismic Gas S/O Valve | 5/6/2026 | SGSOV Approved | JOSH MEISTER |
| Final | 5/11/2026 | OK to Issue CofO | JOSH MEISTER |
| Green Building Final | 5/11/2026 | Approved | JOSH MEISTER |