20217-20219 W WELLS DR 91364

Certificate Information: 20217-20219 W WELLS DR 91364

Application / Permit
25014-20000-03098
Plan Check / Job No.
B25VN19489
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT PORTION OF (E) SFD WITH 18'-4" X 7' ADDITION TO 420.3 SF ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (e).
Permit Issued
Issued on 8/15/2025
Issuing Office
Current Status
CofO in Progress on 3/31/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/8/2025 APPLICANT
Assigned to Plan Check Engineer 7/14/2025 ARTIN ZARUKIAN
Corrections Issued 7/14/2025 ARTIN ZARUKIAN
Building Plans Picked Up 7/16/2025 APPLICANT
Applicant returned to address corrections 8/4/2025 SEWADA ZADOORIAN MILAGARDI
Issued 8/15/2025 APPLICANT
CofO in Progress 3/31/2026 SEAN WIRCH

Permit Application Clearance Information

Address approval Cleared 7/17/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 7/17/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 7/17/2025 MICHAEL BROWN
Sewer availability Cleared 7/17/2025 MICHAEL BROWN
Grading Pre-Inspection Cleared 8/15/2025 ARTIN ZARUKIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/9/2025 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 10/17/2025 Partial Approval JOHN HAYES
Underground Mechanical 10/17/2025 Approved JOHN HAYES
Footing/Foundation/Slab 10/24/2025 Corrections Issued MORRIS JACKSON
Special/Order Compliance 10/24/2025 Partial Inspection SEAN WIRCH
Deputy Drilled-In Anchors 10/27/2025 Partial Approval SEAN WIRCH
Footing/Foundation/Slab 10/28/2025 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 11/10/2025 No Access for Inspection JOHN HAYES
ELECTRICAL-Rough 1/16/2026 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 1/16/2026 Partial Approval SEAN WIRCH
HVAC-Rough 1/16/2026 Approved SEAN WIRCH
PLUMBING-Rough 1/16/2026 Approved SEAN WIRCH
BUILDING-Rough-Frame 1/23/2026 Approved SEAN WIRCH
Green Building Rough 1/23/2026 Approved SEAN WIRCH
Insulation 1/30/2026 Approved SEAN WIRCH
Interior/Exterior Lathing 1/30/2026 Partial Approval SEAN WIRCH
Drywall Nailing 2/9/2026 Approved SEAN WIRCH
Interior/Exterior Lathing 2/9/2026 Approved SEAN WIRCH
Final 3/20/2026 No Access for Inspection JOHN HAYES
Footing/Foundation/Slab 3/20/2026 Not Ready for Inspection JOHN HAYES
Green Building Final 3/20/2026 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 3/20/2026 SGSOV Not Ready JOHN HAYES
Smoke Detectors 3/20/2026 No Access for Inspection JOHN HAYES
ELECTRICAL-Final 3/27/2026 Approved SEAN WIRCH
Final 3/27/2026 OK to Issue CofO SEAN WIRCH
Footing/Foundation/Slab 3/27/2026 Approved SEAN WIRCH
HVAC-Final 3/27/2026 Approved SEAN WIRCH
PLUMBING-Final 3/27/2026 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 3/27/2026 SGSOV Approved SEAN WIRCH
Smoke Detectors 3/27/2026 Approved SEAN WIRCH