11920 W RATNER ST 91605
Certificate Information: 11920 W RATNER ST 91605
- Application / Permit
- 25014-20000-03072
- Plan Check / Job No.
- B25VN19305
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 9'-0" X 35'-11.5" ADDITION AND MAJOR REMODEL TO EXISTING SINGLE STORY SINGLE FAMILY DWELLING *NFPA-13D FIRE SPRINKLERED THROUGHOUT
- Permit Issued
- Issued on 10/15/2025
- Issuing Office
- Current Status
- Issued on 10/15/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2025 | DANIEL ABRAMYAN |
| Corrections Issued | 7/14/2025 | DANIEL ABRAMYAN |
| Quality Review Completed | 7/17/2025 | OMID HEDAYAT |
| Building Plans Picked Up | 8/1/2025 | APPLICANT |
| Plan Check Approved | 10/15/2025 | RAPHAEL ROSAS |
| Issued | 10/15/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/14/2025 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2025 | TREVOR QUAN |
| Sewer availability | Cleared | 10/15/2025 | TREVOR QUAN |
Contact Information
| Contractor | Creative Innovation Developers Inc; Lic. No.: 1035641-B | 1812 W BURBANK BLVD STE 1032 BURBANK, CA 91506 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/20/2025 | Approved | MATTHEW NELSON |
| Pre-Inspection | 11/20/2025 | Corrections Issued | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2025 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 12/24/2025 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 12/24/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2026 | Partial Approval | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 1/27/2026 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2026 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/18/2026 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 3/18/2026 | Approved | MATTHEW NELSON |
| Gas Test | 3/18/2026 | Approved | MATTHEW NELSON |
| Green Building Rough | 3/18/2026 | Approved | MATTHEW NELSON |
| HVAC-Rough | 3/18/2026 | Corrections Issued | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/18/2026 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 3/18/2026 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/25/2026 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Rough | 3/25/2026 | Corrections Issued | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/25/2026 | Partial Approval | MATTHEW NELSON |
| Shower Pan | 3/25/2026 | Approved | MATTHEW NELSON |
| HVAC-Rough | 4/1/2026 | Approved | MATTHEW NELSON |
| Insulation | 4/1/2026 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 4/7/2026 | Corrections Issued | MATTHEW NELSON |
| Drywall Nailing | 5/12/2026 | Approved | MATTHEW NELSON |