6657 N BALCOM AVE 91335

Certificate Information: 6657 N BALCOM AVE 91335

Application / Permit
25014-20000-03067
Plan Check / Job No.
B25VN19260
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING 337 SF DETACHED GARAGE AND NEW 124 ADDITION TO NEW 461 SF ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(b)(1). WORK DONE PER WFPP.
Permit Issued
Issued on 7/21/2025
Issuing Office
Current Status
Issued on 7/21/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/7/2025 APPLICANT
Assigned to Plan Check Engineer 7/10/2025 MADISON ODELL
Corrections Issued 7/10/2025 MADISON ODELL
Building Plans Picked Up 7/11/2025 APPLICANT
Issued 7/21/2025 APPLICANT

Permit Application Clearance Information

ZI Cleared 7/18/2025 FIPE LEILUA
Address approval Cleared 7/21/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 7/21/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 7/21/2025 SAFA JAVANMARDI
Sewer availability Cleared 7/21/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/14/2026 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 4/16/2026 Approved ARUTYUN MADATYAN
Footing/Foundation/Slab 4/16/2026 Approved ARUTYUN MADATYAN
PLUMBING-Rough 4/20/2026 Partial Approval ARUTYUN MADATYAN
Sewer 4/20/2026 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 5/13/2026 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 5/13/2026 Partial Approval ARUTYUN MADATYAN
HVAC-Rough 5/13/2026 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 5/13/2026 Corrections Issued ARUTYUN MADATYAN
BUILDING-Rough-Frame 5/15/2026 Corrections Issued ARUTYUN MADATYAN
Green Building Rough 5/15/2026 Not Ready for Inspection ARUTYUN MADATYAN
Wood Frame 5/15/2026 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Rough 5/20/2026 Approved ARUTYUN MADATYAN
Rough-Elec/Plmb/HVAC 5/20/2026 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 5/26/2026 Approved ARUTYUN MADATYAN
Green Building Rough 5/26/2026 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 5/26/2026 Corrections Issued ARUTYUN MADATYAN
Insulation 5/27/2026 Not Ready for Inspection ARUTYUN MADATYAN
Insulation 5/28/2026 Approved ALEXANDER HANDY
Interior/Exterior Lathing 5/28/2026 Partial Approval ALEXANDER HANDY
Drywall Nailing 6/1/2026 Approved ARUTYUN MADATYAN
Shower Pan 6/1/2026 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 6/5/2026 No Result Entered ARUTYUN MADATYAN