8101 N LURLINE AVE 91306
Certificate Information: 8101 N LURLINE AVE 91306
- Application / Permit
- 25014-20000-03045
- Plan Check / Job No.
- B25VN19179
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Addition of a recreational room attached to existing S.F.D.
- Permit Issued
- Issued on 10/3/2025
- Issuing Office
- Current Status
- CofO Issued on 6/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2025 | CAROLEAN BASMA |
| Corrections Issued | 7/15/2025 | CAROLEAN BASMA |
| Plan Check Approved | 9/12/2025 | CAROLEAN BASMA |
| Issued | 10/3/2025 | APPLICANT |
| CofO in Progress | 4/7/2026 | ALEXANDER HANDY |
| Permit Finaled | 6/2/2026 | JOHN JANSON |
| CofO Issued | 6/2/2026 | JOHN JANSON |
| Permit Finaled | 6/2/2026 | JOHN JANSON |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/21/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 8/1/2025 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mokri, - Arganeh, Fattaneh; Lic. No.: C52608 | 30281 GRANDE VISTA AVENUE LAGUNA NIGUEL, CA 92677 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/30/2025 | Partial Approval | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 1/15/2026 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 1/15/2026 | Partial Approval | ALEXANDER HANDY |
| Deputy Drilled-In Anchors | 1/16/2026 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 1/20/2026 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 2/6/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2026 | Approved | ALEXANDER HANDY |
| Green Building Rough | 2/6/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 2/6/2026 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 2/18/2026 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 2/18/2026 | Approved | ALEXANDER HANDY |
| Green Building Rough | 2/18/2026 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 2/18/2026 | Approved | ALEXANDER HANDY |
| Insulation | 2/23/2026 | Approved | DAVID FASTIGGI |
| Interior/Exterior Lathing | 2/23/2026 | Approved | DAVID FASTIGGI |
| Drywall Nailing | 3/6/2026 | Approved | DAVID FASTIGGI |
| Interior/Exterior Lathing | 3/6/2026 | Approved | DAVID FASTIGGI |
| ELECTRICAL-Final | 4/6/2026 | Approved | ALEXANDER HANDY |
| Final | 4/6/2026 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 4/6/2026 | Approved | ALEXANDER HANDY |
| HVAC-Final | 4/6/2026 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 4/6/2026 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 4/6/2026 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 4/6/2026 | Approved | ALEXANDER HANDY |