8424 N LEHIGH AVE 91352

Certificate Information: 8424 N LEHIGH AVE 91352

Application / Permit
25014-20000-03040
Plan Check / Job No.
B25VN19168
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE WITH ADDITIONS INTO A (N) 2-STORY ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(b)(1) WITH ATTACHED COVERED PORCH PER ENGINEERING
Permit Issued
Issued on 9/29/2025
Issuing Office
Current Status
Issued on 9/29/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/3/2025 APPLICANT
Assigned to Plan Check Engineer 7/17/2025 ALFRED RAMIREZ
Corrections Issued 7/20/2025 ALFRED RAMIREZ
Quality Review Completed 7/25/2025 STEVEN KIM
Building Plans Picked Up 8/6/2025 APPLICANT
Plan Check Approved 9/29/2025 ALFRED RAMIREZ
Issued 9/29/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/11/2025 TREVOR QUAN
Roof/Waste drainage to street Cleared 8/11/2025 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 8/12/2025 TREVOR QUAN
Sewer availability Cleared 8/12/2025 TREVOR QUAN
Construction near power lines Cleared 9/24/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/28/2025 Partial Approval DAVID ANDERSON
Deputy Drilled-In Anchors 10/31/2025 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 10/31/2025 Approved DAVID ANDERSON
Deputy Drilled-In Anchors 11/10/2025 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 11/10/2025 Partial Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 12/1/2025 Approved DAVID ANDERSON
ELECTRICAL-Rough 12/19/2025 Approved MATTHEW NELSON
HVAC-Rough 12/19/2025 Approved MATTHEW NELSON
PLUMBING-Rough 12/19/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 12/29/2025 No Access for Inspection MICHAEL CORTEZ
BUILDING-Rough-Frame 1/2/2026 Partial Approval DAVID ANDERSON
Insulation 1/12/2026 Corrections Issued DAVID ANDERSON
Interior/Exterior Lathing 1/12/2026 Partial Approval DAVID ANDERSON
Shower Pan 1/12/2026 Approved DAVID ANDERSON
Drywall Nailing 1/26/2026 Approved MATTHEW NELSON
Green Building Rough 1/26/2026 Approved MATTHEW NELSON
Interior/Exterior Lathing 1/26/2026 Approved MATTHEW NELSON
BUILDING-Rough-Frame 4/14/2026 Approved DAVID ANDERSON
Final 4/14/2026 Corrections Issued DAVID ANDERSON
Green Building Final 4/14/2026 Not Ready for Inspection DAVID ANDERSON
MERV13>=Final 4/14/2026 Approved DAVID ANDERSON
MERV13>=Rough 4/14/2026 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 4/14/2026 SGSOV Approved DAVID ANDERSON
Smoke Detectors 4/14/2026 Approved DAVID ANDERSON