13352 W GARBER ST 91331
Certificate Information: 13352 W GARBER ST 91331
- Application / Permit
- 25014-20000-03029
- Plan Check / Job No.
- B25VN19106
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 95 SQ FT AND CONVERT EXISTING 339 SQ FT DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d); ADD 20' X 20' PATIO COVER
- Permit Issued
- Issued on 10/17/2025
- Issuing Office
- Current Status
- Issued on 10/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2025 | SELLA BENYAMIN |
| Corrections Issued | 7/24/2025 | SELLA BENYAMIN |
| Quality Review Completed | 7/31/2025 | STEVEN KIM |
| Building Plans Picked Up | 8/1/2025 | APPLICANT |
| Plan Check Approved | 9/11/2025 | SELLA BENYAMIN |
| Issued | 10/17/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/14/2025 | DERRICK MAGEE |
| Roof/Waste drainage to street | Cleared | 8/14/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 8/28/2025 | DERRICK MAGEE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/12/2025 | Partial Approval | MICHEL ABAJAN |
| Pre-Inspection | 12/12/2025 | Partial Inspection | MICHEL ABAJAN |
| Sewer | 12/12/2025 | Approved | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 12/19/2025 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 12/19/2025 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 12/19/2025 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 12/19/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/19/2025 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/2/2026 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2026 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 3/2/2026 | Partial Inspection | MICHEL ABAJAN |
| METHANE-Rough | 3/2/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/2/2026 | Approved | MICHEL ABAJAN |
| Sewer | 3/2/2026 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 3/2/2026 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/27/2026 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2026 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 3/27/2026 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 3/27/2026 | Approved | MICHEL ABAJAN |
| Insulation | 4/29/2026 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/29/2026 | Partial Approval | MATTHEW NELSON |
| Drywall Nailing | 5/15/2026 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/15/2026 | Approved | MICHEL ABAJAN |