8139-8141 N ETIWANDA AVE 91335

Certificate Information: 8139-8141 N ETIWANDA AVE 91335

Application / Permit
25014-20000-03021
Plan Check / Job No.
B25VN19062
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New addition at the rear of the SFD. All work per Engineer.
Permit Issued
Issued on 7/17/2025
Issuing Office
Current Status
CofO Issued on 4/25/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/3/2025 APPLICANT
Assigned to Plan Check Engineer 7/3/2025 NAREG ATARIAN
Corrections Issued 7/3/2025 NAREG ATARIAN
Plan Check Approved 7/17/2025 ALEC MOUSAKHANIAN
Issued 7/17/2025 APPLICANT
CofO in Progress 4/3/2026 TROY SANDERS
Permit Finaled 4/25/2026 MICHAEL PELHAM
CofO Issued 4/25/2026 MICHAEL PELHAM
Permit Finaled 4/25/2026 MICHAEL PELHAM

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/12/2025 COLIN LOREDO
Roof/Waste drainage to street Cleared 7/12/2025 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Khazra,, Afshin; Lic. No.: C50250 22855 PAUL REVERE DR      CALABASAS, CA 91302

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/28/2025 Corrections Issued JUAN ALVARADO
Underground Mechanical 9/4/2025 Approved JUAN ALVARADO
Deputy Drilled-In Anchors 9/11/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 9/11/2025 Corrections Issued JUAN ALVARADO
Footing/Foundation/Slab 9/18/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 10/9/2025 Corrections Issued JUAN ALVARADO
Green Building Rough 10/9/2025 Not Ready for Inspection JUAN ALVARADO
BUILDING-Rough-Frame 10/16/2025 Not Ready for Inspection JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 10/16/2025 Corrections Issued JUAN ALVARADO
Green Building Rough 10/16/2025 Not Ready for Inspection JUAN ALVARADO
Wood Frame 10/16/2025 Not Ready for Inspection JUAN ALVARADO
BUILDING-Rough-Frame 10/23/2025 Partial Inspection JUAN ALVARADO
ELECTRICAL-Rough 10/23/2025 Not Ready for Inspection JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 10/23/2025 Approved JUAN ALVARADO
Green Building Rough 10/23/2025 Not Ready for Inspection JUAN ALVARADO
PLUMBING-Rough 10/23/2025 Not Ready for Inspection JUAN ALVARADO
BUILDING-Rough-Frame 10/29/2025 Not Ready for Inspection JUAN ALVARADO
ELECTRICAL-Rough 10/29/2025 Approved JUAN ALVARADO
Green Building Rough 10/29/2025 Not Ready for Inspection JUAN ALVARADO
BUILDING-Rough-Frame 10/31/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 10/31/2025 Approved ARUTYUN MADATYAN
Green Building Rough 10/31/2025 Approved ARUTYUN MADATYAN
HVAC-Rough 10/31/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 10/31/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 10/31/2025 Approved ARUTYUN MADATYAN
Insulation 11/4/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 11/4/2025 Approved KRISTEN CAUSEY
Drywall Nailing 11/14/2025 Approved JUAN ALVARADO
Shower Pan 11/14/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 11/19/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 2/5/2026 Approved JUAN ALVARADO
Final 2/5/2026 Corrections Issued JUAN ALVARADO
Green Building Final 2/5/2026 Approved JUAN ALVARADO
HVAC-Final 2/5/2026 Approved JUAN ALVARADO
PLUMBING-Final 2/5/2026 Approved JUAN ALVARADO
Smoke Detectors 2/5/2026 Approved JUAN ALVARADO
Final 4/2/2026 OK to Issue CofO TROY SANDERS