11746 W WOODBINE ST 90066
Certificate Information: 11746 W WOODBINE ST 90066
- Application / Permit
- 25014-20000-03011
- Plan Check / Job No.
- B25VN19036
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- FRONT ADDITION TO (E) SINGLE FAMILY DWELLING AND REFRAME PORTION OF (E) SINGLE FAMILY DWELLING. WORK PER ENGINEER.
- Permit Issued
- Issued on 7/17/2025
- Issuing Office
- Current Status
- CofO Issued on 3/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2025 | GURUNATH NESARAJAH |
| Corrections Issued | 7/2/2025 | GURUNATH NESARAJAH |
| Plan Check Approved | 7/17/2025 | GIOVANNY CHAVEZ |
| Issued | 7/17/2025 | APPLICANT |
| CofO in Progress | 2/25/2026 | ARAM AVEDISIAN |
| Permit Finaled | 3/3/2026 | RICHARD STEINBACH |
| CofO Issued | 3/3/2026 | RICHARD STEINBACH |
| Permit Finaled | 3/3/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 7/7/2025 | MICHAEL BROWN |
| ZI | Cleared | 7/10/2025 | BRENNEN OBETO |
| Specific Plan | Cleared | 7/11/2025 | RICHARD WOO |
| Grading Pre-Inspection | Cleared | 7/15/2025 | LANNY MERRICK |
Contact Information
| Contractor | Built To Perfection Inc; Lic. No.: 837987-B | 22222 SHERMAN WAY #202 CANOGA PARK, CA 91303 |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/15/2025 | Conditional Approval | MICHAEL PELHAM |
| Deputy Drilled-In Anchors | 9/16/2025 | Approved | KIRK SANDERS |
| Footing/Foundation/Slab | 9/16/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 9/26/2025 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 11/7/2025 | No Access for Inspection | KIRK SANDERS |
| Wood Frame | 11/7/2025 | No Access for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 11/12/2025 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 11/20/2025 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 11/20/2025 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 11/20/2025 | Approved | STEPHANIE SWANSON |
| Insulation | 12/4/2025 | Approved | KIRK SANDERS |
| Drywall Nailing | 12/11/2025 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 2/25/2026 | Approved | ARAM AVEDISIAN |
| Final | 2/25/2026 | OK to Issue CofO | ARAM AVEDISIAN |
| Green Building Final | 2/25/2026 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 2/25/2026 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 2/25/2026 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 2/25/2026 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 2/25/2026 | Approved | ARAM AVEDISIAN |