12823 W MARTHA ST 91607
Certificate Information: 12823 W MARTHA ST 91607
- Application / Permit
- 25014-20000-02984
- Plan Check / Job No.
- B25VN18707
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO THE REAR OF THE (E) SINGLE FAMILY DWELLING TO ENLARGE THE (E) BEDROOM WITH AN INTERIOR REMODEL TO CREATE A NEW BATHROOM.
- Permit Issued
- Issued on 7/3/2025
- Issuing Office
- Current Status
- CofO Issued on 2/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2025 | GIOVANNY CHAVEZ |
| Corrections Issued | 6/30/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 7/3/2025 | NAREG ATARIAN |
| Issued | 7/3/2025 | APPLICANT |
| CofO in Progress | 1/9/2026 | CRAIG DAVIS |
| Permit Finaled | 2/3/2026 | RUBEN SALAS |
| CofO Issued | 2/3/2026 | RUBEN SALAS |
| Permit Finaled | 2/3/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/1/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 7/2/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/29/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Reinf. Concrete | 7/31/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/1/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Green Building Rough | 8/8/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Insulation | 8/13/2025 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 8/13/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Green Building Rough | 8/14/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 9/18/2025 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2025 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 9/18/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 9/18/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/26/2025 | Approved | WAYNE REGESTER |
| Green Building Rough | 9/26/2025 | Approved | WAYNE REGESTER |
| Insulation | 10/7/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 10/7/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Drywall Nailing | 10/10/2025 | Approved | CHRISTOPHER MORFIN |
| Shower Pan | 10/10/2025 | Approved | CHRISTOPHER MORFIN |
| Interior/Exterior Lathing | 10/21/2025 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 12/22/2025 | Corrections Issued | CRAIG DAVIS |
| HVAC-Final | 12/22/2025 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Final | 12/22/2025 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Final | 1/8/2026 | Approved | CRAIG DAVIS |
| Final | 1/8/2026 | OK to Issue CofO | CRAIG DAVIS |
| Green Building Final | 1/8/2026 | Approved | CRAIG DAVIS |
| HVAC-Final | 1/8/2026 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 1/8/2026 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 1/8/2026 | SGSOV Approved | CRAIG DAVIS |
| Smoke Detectors | 1/8/2026 | Approved | CRAIG DAVIS |