7221-7223 N KRAFT AVE 91605
Certificate Information: 7221-7223 N KRAFT AVE 91605
- Application / Permit
- 25014-20000-02903
- Plan Check / Job No.
- B25VN18224
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING ATTACHED GARAGE AND NEW ADDITION TO NEW JUNIOR ACCESSORY DWELLING UNIT PER GCS 66323(a)(1) AND 66333. WORK DONE PER WFPP.
- Permit Issued
- Issued on 7/17/2025
- Issuing Office
- Current Status
- CofO Issued on 4/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2025 | MADISON ODELL |
| Corrections Issued | 6/28/2025 | MADISON ODELL |
| Applicant returned to address corrections | 7/15/2025 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 7/17/2025 | MIROOSH KHACHATOORIAN |
| Issued | 7/17/2025 | APPLICANT |
| CofO in Progress | 3/26/2026 | GAREN HAYRAPETYAN |
| Permit Finaled | 4/9/2026 | RUBEN SALAS |
| CofO Issued | 4/9/2026 | RUBEN SALAS |
| Permit Finaled | 4/9/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/1/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 7/1/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 7/1/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/26/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 10/1/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 10/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 10/27/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 11/14/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 12/5/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 12/5/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 12/5/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 12/10/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 12/10/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 12/10/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 12/16/2025 | No Access for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 12/16/2025 | No Access for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 12/19/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 12/29/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 12/29/2025 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 12/31/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 12/31/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 1/8/2026 | Approved | JOSE AVILA |
| PLUMBING-Final | 1/8/2026 | Approved | JOSE AVILA |
| HVAC-Rough | 1/13/2026 | Partial Inspection | JOSE AVILA |
| Shower Pan | 1/13/2026 | Approved | JOSE AVILA |
| Drywall Nailing | 1/21/2026 | Not Ready for Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 1/22/2026 | Approved | JOSE AVILA |
| Green Building Rough | 1/22/2026 | Approved | JOSE AVILA |
| Insulation | 1/22/2026 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 2/5/2026 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 3/9/2026 | Approved | GAREN HAYRAPETYAN |
| Underground Mechanical | 3/9/2026 | Partial Approval | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 3/19/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Final | 3/19/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 3/19/2026 | Approved | GAREN HAYRAPETYAN |
| Green Building Final | 3/19/2026 | Approved | GAREN HAYRAPETYAN |
| HVAC-Final | 3/19/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 3/19/2026 | SGSOV Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 3/19/2026 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Smoke Detectors | 3/19/2026 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 3/26/2026 | Approved | GAREN HAYRAPETYAN |
| Final | 3/26/2026 | OK to Issue CofO | GAREN HAYRAPETYAN |
| HVAC-Final | 3/26/2026 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Final | 3/26/2026 | Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 3/26/2026 | Approved | GAREN HAYRAPETYAN |