7221-7223 N KRAFT AVE 91605

Certificate Information: 7221-7223 N KRAFT AVE 91605

Application / Permit
25014-20000-02903
Plan Check / Job No.
B25VN18224
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING ATTACHED GARAGE AND NEW ADDITION TO NEW JUNIOR ACCESSORY DWELLING UNIT PER GCS 66323(a)(1) AND 66333. WORK DONE PER WFPP.
Permit Issued
Issued on 7/17/2025
Issuing Office
Current Status
CofO Issued on 4/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/25/2025 APPLICANT
Assigned to Plan Check Engineer 6/27/2025 MADISON ODELL
Corrections Issued 6/28/2025 MADISON ODELL
Applicant returned to address corrections 7/15/2025 MIROOSH KHACHATOORIAN
Plan Check Approved 7/17/2025 MIROOSH KHACHATOORIAN
Issued 7/17/2025 APPLICANT
CofO in Progress 3/26/2026 GAREN HAYRAPETYAN
Permit Finaled 4/9/2026 RUBEN SALAS
CofO Issued 4/9/2026 RUBEN SALAS
Permit Finaled 4/9/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/1/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 7/1/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 7/1/2025 SAFA JAVANMARDI
Sewer availability Cleared 7/1/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/26/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 10/1/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 10/21/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 10/27/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 11/14/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 11/14/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/5/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 12/5/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 12/5/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 12/5/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 12/10/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/10/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Rough 12/10/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 12/10/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 12/16/2025 No Access for Inspection OGANES TARAKHCHYAN
Green Building Rough 12/16/2025 No Access for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/19/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 12/19/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 12/29/2025 Corrections Issued JOSE AVILA
PLUMBING-Final 12/29/2025 Corrections Issued JOSE AVILA
HVAC-Rough 12/31/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 12/31/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 1/8/2026 Approved JOSE AVILA
PLUMBING-Final 1/8/2026 Approved JOSE AVILA
HVAC-Rough 1/13/2026 Partial Inspection JOSE AVILA
Shower Pan 1/13/2026 Approved JOSE AVILA
Drywall Nailing 1/21/2026 Not Ready for Inspection JOSE AVILA
BUILDING-Rough-Frame 1/22/2026 Approved JOSE AVILA
Green Building Rough 1/22/2026 Approved JOSE AVILA
Insulation 1/22/2026 Approved JOSE AVILA
Interior/Exterior Lathing 2/5/2026 Approved MICHAEL CORTEZ
Drywall Nailing 3/9/2026 Approved GAREN HAYRAPETYAN
Underground Mechanical 3/9/2026 Partial Approval GAREN HAYRAPETYAN
ELECTRICAL-Final 3/19/2026 Corrections Issued GAREN HAYRAPETYAN
Final 3/19/2026 Corrections Issued GAREN HAYRAPETYAN
Footing/Foundation/Slab 3/19/2026 Approved GAREN HAYRAPETYAN
Green Building Final 3/19/2026 Approved GAREN HAYRAPETYAN
HVAC-Final 3/19/2026 Corrections Issued GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 3/19/2026 SGSOV Approved GAREN HAYRAPETYAN
Service/Power Release 3/19/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Smoke Detectors 3/19/2026 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 3/26/2026 Approved GAREN HAYRAPETYAN
Final 3/26/2026 OK to Issue CofO GAREN HAYRAPETYAN
HVAC-Final 3/26/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Final 3/26/2026 Approved GAREN HAYRAPETYAN
Service/Power Release 3/26/2026 Approved GAREN HAYRAPETYAN