10833 N GLORIA AVE 91344
Certificate Information: 10833 N GLORIA AVE 91344
- Application / Permit
- 25014-20000-02883
- Plan Check / Job No.
- B25VN18097
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. Addition and Remodel (E) SFD W/Attached garage. Remove patio cover. Per engineering design.
- Permit Issued
- Issued on 7/31/2025
- Issuing Office
- Current Status
- Issued on 7/31/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2025 | ALFREDO JARA |
| Corrections Issued | 7/8/2025 | ALFREDO JARA |
| Plan Check Approved | 7/30/2025 | ALFREDO JARA |
| Issued | 7/31/2025 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 7/9/2025 | JASON CHAN |
| Roof/Waste drainage to street | Cleared | 7/16/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 7/16/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/11/2025 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 9/12/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 9/25/2025 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 9/25/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2026 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 3/10/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/10/2026 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 3/10/2026 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 3/10/2026 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 3/10/2026 | Partial Approval | JENNIFER RABUCHIN |
| MERV13>=Rough | 3/10/2026 | Approved | JENNIFER RABUCHIN |
| Insulation | 4/2/2026 | Approved | JOSE AVILA |
| Drywall Nailing | 4/14/2026 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 5/18/2026 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 5/21/2026 | Approved | CHRISTOPHER ROJAS |