7541 1/2 N CLAYBECK AVE 91505
Certificate Information: 7541 1/2 N CLAYBECK AVE 91505
- Application / Permit
- 25014-20000-02849
- Plan Check / Job No.
- B25VN17806
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN PROPOSED 15'-6" X 19'-6" 2-STORY ADDITION W/ ROOFTOP DECK TO (E) ADU. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/19/2026
- Issuing Office
- Current Status
- Issued on 1/19/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2025 | RAPHAEL ROSAS |
| Corrections Issued | 7/21/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 7/24/2025 | STEVEN KIM |
| Applicant returned to address corrections | 11/20/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 12/31/2025 | RAPHAEL ROSAS |
| Issued | 1/19/2026 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 10/30/2025 | JASON CHAN |
| Roof/Waste drainage to street | Cleared | 11/20/2025 | JESUS LUNA |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2025 | JESUS LUNA |
| Sewer availability | Cleared | 11/21/2025 | JESUS LUNA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21731 VENTURA BLVD SUITE 110 WOODLAND HILLS, CA 91364 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Drywall Nailing | 7/27/2026 |
| Interior/Exterior Lathing | 7/27/2026 |
| Green Building Rough | 7/27/2026 |
Inspection Request History
| Deputy Drilled-In Anchors | 2/19/2026 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 2/23/2026 | Corrections Issued | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 3/12/2026 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 7/9/2026 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 7/9/2026 | Not Ready for Inspection | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 7/9/2026 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2026 | Partial Approval | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 7/17/2026 | Approved | MATTHEW NELSON |
| Wood Frame | 7/17/2026 | Approved | MATTHEW NELSON |
| Insulation | 7/21/2026 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 7/21/2026 | Not Ready for Inspection | MATTHEW NELSON |