EPLAN Garage conversion and addition to ADU. work per WFPP
Permit Issued
Issued on 1/8/2026
Issuing Office
Current Status
CofO Issued on 6/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2025 APPLICANT
Assigned to Plan Check Engineer 6/27/2025 NEHEMIAS RAMOS
Corrections Issued 6/30/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 8/4/2025 NEHEMIAS RAMOS
Plan Check Approved 1/8/2026 NEHEMIAS RAMOS
Issued 1/8/2026 APPLICANT
CofO in Progress 4/10/2026 JAVIER RAMOS JR
Permit Finaled 6/23/2026 RUBEN SALAS
CofO Issued 6/23/2026 RUBEN SALAS
Permit Finaled 6/23/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/7/2025 DERRICK MAGEE
Roof/Waste drainage to street Cleared 7/7/2025 DERRICK MAGEE
Sewer availability Cleared 7/7/2025 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 7/14/2025 DERRICK MAGEE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/9/2026 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 2/9/2026 Partial Approval JAVIER RAMOS JR
Pre-Inspection 2/9/2026 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 2/25/2026 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 2/25/2026 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 3/4/2026 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 3/4/2026 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/4/2026 Approved JAVIER RAMOS JR
HVAC-Rough 3/4/2026 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 3/4/2026 Approved JAVIER RAMOS JR
PLUMBING-Rough 3/4/2026 Approved JAVIER RAMOS JR
Sewer 3/4/2026 Approved JAVIER RAMOS JR
Underground Mechanical 3/4/2026 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 3/31/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 3/31/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 3/31/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 3/31/2026 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 3/31/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 3/31/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/2/2026 Approved JAVIER RAMOS JR
Drywall Nailing 4/2/2026 Approved JAVIER RAMOS JR
ELECTRICAL-Final 4/2/2026 Approved JAVIER RAMOS JR
Final 4/2/2026 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 4/2/2026 Approved JAVIER RAMOS JR
HVAC-Final 4/2/2026 Approved JAVIER RAMOS JR
Insulation 4/2/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 4/2/2026 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/2/2026 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 4/2/2026 Approved JAVIER RAMOS JR
Final 4/10/2026 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 4/10/2026 Approved JAVIER RAMOS JR