7638-7640 N AMPERE AVE 91605
Certificate Information: 7638-7640 N AMPERE AVE 91605
- Application / Permit
- 25014-20000-02794
- Plan Check / Job No.
- B25VN17433
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: ADDITION & CONVERSION OF EXISTING ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT (ADU) PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 8/12/2025
- Issuing Office
- Current Status
- Issued on 8/12/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/25/2025 | OMAR GARNICA |
| Corrections Issued | 6/26/2025 | OMAR GARNICA |
| Plan Check Approved | 8/11/2025 | MOHAMMAD ESMAILI |
| Issued | 8/12/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/23/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 7/23/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 7/24/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/12/2025 | Partial Approval | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 1/8/2026 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 1/8/2026 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/18/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 3/18/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/18/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 3/25/2026 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2026 | Partial Approval | GAREN HAYRAPETYAN |
| HVAC-Rough | 3/25/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 3/25/2026 | Approved | GAREN HAYRAPETYAN |
| Wood Frame | 4/2/2026 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 4/13/2026 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 4/21/2026 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 4/21/2026 | Approved | GAREN HAYRAPETYAN |
| Insulation | 4/21/2026 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 4/21/2026 | Partial Approval | GAREN HAYRAPETYAN |
| Drywall Nailing | 5/5/2026 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 5/5/2026 | Approved | MATTHEW NELSON |