7449 N ALDEA AVE 91406

Certificate Information: 7449 N ALDEA AVE 91406

Application / Permit
25014-20000-02786
Plan Check / Job No.
B25VN17376
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ADDITION TO THE (E) SINGLE-FAMILY DWELLING. WORK PER WFPP.
Permit Issued
Issued on 7/1/2025
Issuing Office
Valley
Current Status
CofO in Progress on 6/5/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/17/2025 APPLICANT
Assigned to Plan Check Engineer 6/17/2025 ALEC MOUSAKHANIAN
Corrections Issued 6/17/2025 ALEC MOUSAKHANIAN
Plan Check Approved 6/30/2025 GIOVANNY CHAVEZ
Issued 7/1/2025 APPLICANT
CofO in Progress 6/5/2026 MICHAEL CORTEZ

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/21/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/24/2025 BIAINA HARITUNIAN
Watercourse Cleared 6/24/2025 BIAINA HARITUNIAN

Contact Information

Architect , ; Lic. No.: C37811 18410 CHARLTON LANE      NORTHRIDGE, CA 91326
Contractor Direct Restoration; Lic. No.: 1005391-B 19528 VENTURA BLVD # 254      TARZANA, CA 91356

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/10/2025 Partial Approval NICHOLAS TROWBRIDGE
Deputy Drilled-In Anchors 7/14/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/15/2025 Approved JACK KARGODORIAN
Green Building Rough 9/11/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Insulation 9/11/2025 Partial Approval GAREN HAYRAPETYAN
BUILDING-Rough-Frame 9/17/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 9/17/2025 Partial Approval GAREN HAYRAPETYAN
Green Building Rough 9/17/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Interior/Exterior Lathing 10/16/2025 Partial Approval WAYNE REGESTER
ELECTRICAL-Rough 12/29/2025 Corrections Issued GAREN HAYRAPETYAN
HVAC-Rough 12/29/2025 Corrections Issued GAREN HAYRAPETYAN
Interior/Exterior Lathing 12/29/2025 Partial Approval GAREN HAYRAPETYAN
PLUMBING-Rough 12/29/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 1/5/2026 Corrections Issued GAREN HAYRAPETYAN
ELECTRICAL-Rough 1/5/2026 Approved GAREN HAYRAPETYAN
Green Building Rough 1/5/2026 Approved GAREN HAYRAPETYAN
HVAC-Rough 1/5/2026 Approved GAREN HAYRAPETYAN
Insulation 1/7/2026 Partial Inspection CRAIG DAVIS
Drywall Nailing 1/20/2026 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 3/26/2026 Partial Approval KIRK SANDERS
Shower Pan 3/26/2026 Approved KIRK SANDERS
BUILDING-Rough-Frame 5/20/2026 Approved MICHAEL CORTEZ
Final 5/20/2026 Corrections Issued MICHAEL CORTEZ
Green Building Final 5/20/2026 Corrections Issued MICHAEL CORTEZ
Smoke Detectors 5/20/2026 Approved MICHAEL CORTEZ
Final 5/27/2026 Corrections Issued MICHAEL CORTEZ
ELECTRICAL-Final 6/4/2026 Approved MICHAEL CORTEZ
Final 6/4/2026 OK to Issue CofO MICHAEL CORTEZ
Green Building Final 6/4/2026 Approved MICHAEL CORTEZ
HVAC-Final 6/4/2026 Approved MICHAEL CORTEZ
PLUMBING-Final 6/4/2026 Approved MICHAEL CORTEZ
Service/Power Release 6/4/2026 Approved MICHAEL CORTEZ