8723 N SEPULVEDA BLVD 91343
Certificate Information: 8723 N SEPULVEDA BLVD 91343
- Application / Permit
- 25014-20000-02746
- Plan Check / Job No.
- B25VN17136
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (16) Grocery Store
- Work Description
- EPLAN***PROPOSED ALETRATION TO GROCERY STORE WITH ADDITION OF CANOPIY AT LOADING AREA
- Permit Issued
- Issued on 10/13/2025
- Issuing Office
- Current Status
- CofO Issued on 7/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2025 | SINA KHOSRAVI |
| Assigned to Zoning Architect | 6/26/2025 | KAITA SAITO |
| Corrections Issued | 7/1/2025 | SINA KHOSRAVI |
| Quality Review Completed | 7/21/2025 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 8/19/2025 | SINA KHOSRAVI |
| Applicant returned to address corrections | 8/27/2025 | SINA KHOSRAVI |
| Applicant returned to address corrections | 9/12/2025 | SINA KHOSRAVI |
| Plan Check Approved | 9/29/2025 | SINA KHOSRAVI |
| Issued | 10/13/2025 | APPLICANT |
| TCO Issued (Expire Date: 01-09-2027) | 7/13/2026 | RICKEY JACKSON |
| CofO in Progress | 7/15/2026 | JOHN KITCKO |
| Permit Finaled | 7/15/2026 | RICKEY JACKSON |
| Permit Finaled | 7/15/2026 | RICKEY JACKSON |
| CofO Issued | 7/15/2026 | RICKEY JACKSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 7/14/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 7/14/2025 | MICHAEL BROWN |
| "Q" conditions | Cleared | 7/15/2025 | RUBEN VASQUEZ |
| ZA Case | Cleared | 7/21/2025 | GRACIELA ACOSTA |
| Green Code | Cleared | 8/5/2025 | MICHAEL AYERS |
| DAS Clearance | Cleared | 8/11/2025 | Aung Soe |
| Zoning Plan Check | Cleared | 8/21/2025 | Aung Soe |
| Food establishment approval | Cleared | 10/4/2025 | LACDHS APPROVED |
Contact Information
| Contractor | Kirkley Corporation Inc; Lic. No.: 408026-B | , |
| Engineer | Jafari,, Masoud -; Lic. No.: NA3812 | , |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/12/2025 | Partial Inspection | ANDREW DORSO |
| Deputy Drilled-In Anchors | 11/18/2025 | Conditional Approval | ANDREW DORSO |
| Deputy Drilled-In Anchors | 11/26/2025 | Conditional Approval | KENNETH ROBERTS |
| Footing/Foundation/Slab | 12/1/2025 | Partial Approval | DEANDRE HOFFMAN |
| Deputy Reinf. Concrete | 12/2/2025 | Conditional Approval | ANDREW DORSO |
| Deputy Drilled-In Anchors | 12/4/2025 | Conditional Approval | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 12/5/2025 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 12/8/2025 | Conditional Approval | ANDREW DORSO |
| Wood Frame | 12/15/2025 | Partial Inspection | ANDREW DORSO |
| Deputy Steel/Welding | 12/16/2025 | Conditional Approval | ANDREW DORSO |
| Deputy Steel/Welding | 12/17/2025 | Conditional Approval | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2025 | Partial Inspection | ANDREW DORSO |
| Deputy Steel/Welding | 12/18/2025 | Conditional Approval | ANDREW DORSO |
| Deputy Steel/Welding | 12/19/2025 | Conditional Approval | ANDREW DORSO |
| Wood Frame | 1/8/2026 | Not Ready for Inspection | JOHN KITCKO |
| Insulation | 1/12/2026 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 1/12/2026 | Partial Inspection | ANDREW DORSO |
| Deputy Steel/Welding | 1/13/2026 | Conditional Approval | ANDREW DORSO |
| Deputy Steel/Welding | 1/26/2026 | Approved | ANDREW DORSO |
| Footing/Foundation/Slab | 1/26/2026 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Concrete | 1/27/2026 | Conditional Approval | ANDREW DORSO |
| Light Gage Steel Frame | 1/29/2026 | Not Ready for Inspection | ANDREW DORSO |
| Drywall Nailing | 1/30/2026 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 1/30/2026 | Partial Inspection | ANDREW DORSO |
| Insulation | 2/3/2026 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 2/6/2026 | Partial Inspection | ANDREW DORSO |
| Deputy Steel/Welding | 2/13/2026 | Conditional Approval | BRIAN KELLY |
| Drywall Nailing | 2/17/2026 | Partial Approval | GREGORY POMISH |
| Light Gage Steel Frame | 2/23/2026 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 3/2/2026 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 3/2/2026 | Partial Inspection | ANDREW DORSO |
| Deputy Steel/Welding | 3/11/2026 | Conditional Approval | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2026 | Partial Inspection | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2026 | Partial Inspection | ANDREW DORSO |
| Interior/Exterior Lathing | 3/27/2026 | Approved | JOHN KITCKO |
| T-Bar Ceiling | 4/2/2026 | Approved | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 4/8/2026 | Approved | ANDREW DORSO |
| Final | 4/29/2026 | Not Ready for Inspection | GREGORY POMISH |
| Footing/Foundation/Slab | 4/29/2026 | Not Ready for Inspection | GREGORY POMISH |
| Green Building Final | 4/29/2026 | Not Ready for Inspection | GREGORY POMISH |
| Green Building Rough | 4/29/2026 | Not Ready for Inspection | GREGORY POMISH |
| Reinforced Masonry Frame | 4/29/2026 | Not Ready for Inspection | GREGORY POMISH |
| SGSOV-Seismic Gas S/O Valve | 4/29/2026 | SGSOV Not Ready | GREGORY POMISH |
| Smoke Detectors | 4/29/2026 | Not Ready for Inspection | GREGORY POMISH |
| Final | 5/28/2026 | Partial Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 5/28/2026 | Approved | JOHN KITCKO |
| Green Building Final | 5/28/2026 | Not Ready for Inspection | JOHN KITCKO |
| Green Building Rough | 5/28/2026 | Not Ready for Inspection | JOHN KITCKO |
| Reinforced Masonry Frame | 5/28/2026 | Partial Inspection | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 5/28/2026 | SGSOV Not Ready | JOHN KITCKO |
| Smoke Detectors | 5/28/2026 | Partial Inspection | JOHN KITCKO |
| Smoke Detectors | 6/26/2026 | Off-Hour Fees Due | |
| Smoke Detectors | 6/26/2026 | Pending Review | |
| Special/Order Compliance | 6/29/2026 | Partial Inspection | JOHN KITCKO |
| Final | 6/30/2026 | Off-Hour Fees Due | |
| Green Building Final | 6/30/2026 | Off-Hour Fees Due | |
| Green Building Rough | 6/30/2026 | Off-Hour Fees Due | |
| Reinforced Masonry Frame | 6/30/2026 | Off-Hour Fees Due | |
| SGSOV-Seismic Gas S/O Valve | 6/30/2026 | Off-Hour Fees Due | |
| Smoke Detectors | 6/30/2026 | Off-Hour Fees Due | |
| Special/Order Compliance | 7/6/2026 | Approved | SEAN POMISH |
| Special/Order Compliance | 7/8/2026 | Partial Inspection | DEANDRE HOFFMAN |
| Final | 7/13/2026 | OK to Issue CofO | JOHN KITCKO |
| Green Building Final | 7/13/2026 | Approved | JOHN KITCKO |
| Green Building Rough | 7/13/2026 | Approved | JOHN KITCKO |
| Reinforced Masonry Frame | 7/13/2026 | Approved | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 7/13/2026 | SGSOV Approved | JOHN KITCKO |
| Smoke Detectors | 7/13/2026 | Approved | JOHN KITCKO |