13956 N CANDLEWOOD DR 91342

Certificate Information: 13956 N CANDLEWOOD DR 91342

Application / Permit
25014-20000-02736
Plan Check / Job No.
B25VN17124
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO AND REMODEL OF EXISTING SINGLE FAMILY DWELLING. WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 7/14/2025
Issuing Office
Current Status
CofO Issued on 3/31/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2025 APPLICANT
Assigned to Plan Check Engineer 6/18/2025 ARTIN ZARUKIAN
Corrections Issued 6/21/2025 ARTIN ZARUKIAN
Building Plans Picked Up 6/23/2025 APPLICANT
Issued 7/14/2025 APPLICANT
CofO in Progress 2/10/2026 KEVIN BERBERYAN
CofO Issued 3/31/2026 RUBEN SALAS
Permit Finaled 3/31/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/23/2025 LEE GUILBEAUX
Sewer availability Cleared 6/23/2025 LEE GUILBEAUX
Watercourse Cleared 6/23/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/23/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/14/2025 SAFA JAVANMARDI
Grading Pre-Inspection Cleared 7/14/2025 ARTIN ZARUKIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/25/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 8/29/2025 Approved MICHEL ABAJAN
Special/Order Compliance 8/29/2025 Partial Inspection RAUL OLAGI
BUILDING-Rough-Frame 9/23/2025 Corrections Issued KEVIN BERBERYAN
Green Building Rough 9/23/2025 Not Ready for Inspection KEVIN BERBERYAN
Wood Frame 9/23/2025 Not Ready for Inspection KEVIN BERBERYAN
BUILDING-Rough-Frame 9/30/2025 Conditional Approval KEVIN BERBERYAN
ELECTRICAL-Rough 9/30/2025 Approved KEVIN BERBERYAN
Green Building Rough 9/30/2025 Not Ready for Inspection KEVIN BERBERYAN
Insulation 10/24/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 10/24/2025 Approved KEVIN BERBERYAN
Drywall Nailing 10/30/2025 Approved KEVIN BERBERYAN
Green Building Rough 10/30/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 12/4/2025 Approved KEVIN BERBERYAN
Final 12/4/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 12/4/2025 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 12/4/2025 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 12/4/2025 Approved KEVIN BERBERYAN
Final 2/10/2026 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 2/10/2026 Approved KEVIN BERBERYAN