7648 N LASAINE AVE 91325

Certificate Information: 7648 N LASAINE AVE 91325

Application / Permit
25014-20000-02724
Plan Check / Job No.
B25VN16962
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert (E) Detached Garage to an Accessory Dwelling Unit w/ addition per LAMC 12.22 A.33(b)(1). Design per licensed engineer.
Permit Issued
Issued on 7/23/2025
Issuing Office
Current Status
CofO Issued on 6/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2025 APPLICANT
Assigned to Plan Check Engineer 6/26/2025 AMY GUEVARRA
Corrections Issued 7/1/2025 AMY GUEVARRA
Plan Check Approved 7/21/2025 CAROLEAN BASMA
Issued 7/23/2025 APPLICANT
CofO in Progress 5/13/2026 MICHAEL CORTEZ
Permit Finaled 6/11/2026 RUBEN SALAS
CofO Issued 6/11/2026 RUBEN SALAS
Permit Finaled 6/11/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/10/2025 DERRICK MAGEE
Roof/Waste drainage to street Cleared 7/11/2025 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 7/14/2025 DERRICK MAGEE
Sewer availability Cleared 7/14/2025 DERRICK MAGEE

Contact Information

Contractor Owner-Builder       ,
Engineer Vartanian,, Albert; Lic. No.: NA39989       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/4/2025 Not Ready for Inspection GAREN HAYRAPETYAN
PLUMBING-Rough 9/4/2025 Corrections Issued GAREN HAYRAPETYAN
Sewer 9/4/2025 Corrections Issued GAREN HAYRAPETYAN
Underground Mechanical 9/4/2025 Approved GAREN HAYRAPETYAN
Deputy Drilled-In Anchors 9/9/2025 Conditional Approval JOAQUIN GREENOUGH
Pre-Inspection 9/9/2025 Approved WAYNE REGESTER
Sewer 9/9/2025 Approved WAYNE REGESTER
Underground Mechanical 9/9/2025 Approved WAYNE REGESTER
Excavation/Setback/Form/Re-Bar 9/22/2025 Approved GAREN HAYRAPETYAN
Footing/Foundation/Slab 9/22/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 12/22/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 12/22/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 12/22/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 12/22/2025 Approved GAREN HAYRAPETYAN
Insulation 1/12/2026 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 1/12/2026 Partial Approval GAREN HAYRAPETYAN
Shower Pan 1/21/2026 Approved MICHAEL CORTEZ
Drywall Nailing 1/27/2026 Approved JACK KARGODORIAN
Interior/Exterior Lathing 1/27/2026 Partial Approval JACK KARGODORIAN
ELECTRICAL-Final 4/21/2026 Corrections Issued KIRK SANDERS
Final 4/21/2026 Corrections Issued KIRK SANDERS
HVAC-Final 4/21/2026 Corrections Issued KIRK SANDERS
PLUMBING-Final 4/21/2026 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 4/21/2026 SGSOV Not Ready KIRK SANDERS
Service/Power Release 4/21/2026 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 4/21/2026 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 5/12/2026 Approved MICHAEL CORTEZ
Final 5/12/2026 OK to Issue CofO MICHAEL CORTEZ
HVAC-Final 5/12/2026 Approved MICHAEL CORTEZ
SGSOV-Seismic Gas S/O Valve 5/12/2026 SGSOV Not Required MICHAEL CORTEZ
Service/Power Release 5/12/2026 Approved MICHAEL CORTEZ
Smoke Detectors 5/12/2026 Approved MICHAEL CORTEZ