4636 N ARRIBA DR 91356
Certificate Information: 4636 N ARRIBA DR 91356
- Application / Permit
- 25014-20000-02706
- Plan Check / Job No.
- B25VN16826
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 1ST AND 2ND FLOOR ADDITION AND REMODEL TO SFD, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING ; "COMPLY WITH DEPARTMENT ORDER effective date 08/29/2025. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 10/17/2025
- Issuing Office
- Valley
- Current Status
- Issued on 10/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2025 | RARES BODEA |
| Corrections Issued | 7/2/2025 | RARES BODEA |
| Quality Review Completed | 7/3/2025 | STEVEN KIM |
| Building Plans Picked Up | 7/22/2025 | APPLICANT |
| Applicant returned to address corrections | 9/17/2025 | RARES BODEA |
| Plan Check Approved | 10/7/2025 | RARES BODEA |
| Plan Check Approved | 10/7/2025 | DANIEL LUERA-SIERRA |
| Issued | 10/17/2025 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 7/26/2025 | COLIN LOREDO |
| BHO/Hillside ordinance | Cleared | 7/26/2025 | COLIN LOREDO |
| BHO/Hillside ordinance | Cleared | 7/26/2025 | COLIN LOREDO |
| BHO/Hillside ordinance | Cleared | 7/26/2025 | COLIN LOREDO |
| BHO/Hillside ordinance | Cleared | 7/26/2025 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 7/26/2025 | COLIN LOREDO |
| Distance to fire station | Cleared | 8/20/2025 | KURT CORRAL |
| Hydrant and Access approval | Cleared | 8/20/2025 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 9/4/2025 | COLIN LOREDO |
| Sewer availability | Cleared | 9/4/2025 | COLIN LOREDO |
| GPI Written Notices | Cleared | 9/17/2025 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 9/17/2025 | RARES BODEA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/20/2025 | Approved | KIM BEAUCHAMP |
| Underground Mechanical | 12/3/2025 | Approved | KIM BEAUCHAMP |
| Deputy Drilled-In Anchors | 12/8/2025 | Approved | KIM BEAUCHAMP |
| Excavation/Setback/Form/Re-Bar | 12/11/2025 | Approved | KIM BEAUCHAMP |
| Footing/Foundation/Slab | 12/11/2025 | Approved | KIM BEAUCHAMP |
| Deputy Wood Construction | 2/23/2026 | Conditional Approval | KIM BEAUCHAMP |
| BUILDING-Rough-Frame | 2/24/2026 | Not Ready for Inspection | KIM BEAUCHAMP |
| Green Building Rough | 2/24/2026 | Not Ready for Inspection | KIM BEAUCHAMP |
| Verify Sprinkler Sign Off | 2/24/2026 | Corrections Issued | KIM BEAUCHAMP |
| Wood Frame | 2/24/2026 | Not Ready for Inspection | KIM BEAUCHAMP |
| HVAC-Rough | 3/26/2026 | Partial Approval | KIM BEAUCHAMP |
| PLUMBING-Rough | 3/26/2026 | Partial Approval | KIM BEAUCHAMP |
| ELECTRICAL-Rough | 5/8/2026 | Approved | JOSE RUBIO |
| Interior/Exterior Lathing | 5/8/2026 | Approved | JOSE RUBIO |
| Insulation | 5/14/2026 | Approved | KIM BEAUCHAMP |
| Drywall Nailing | 5/29/2026 | Partial Inspection | JOSE RUBIO |
| Green Building Rough | 5/29/2026 | Approved | JOSE RUBIO |
| Interior/Exterior Lathing | 5/29/2026 | Approved | JOSE RUBIO |
| Shower Pan | 5/29/2026 | Partial Inspection | JOSE RUBIO |
| Drywall Nailing | 6/2/2026 | Approved | KIM BEAUCHAMP |
| Shower Pan | 6/2/2026 | Partial Approval | KIM BEAUCHAMP |