12561 W INDIANAPOLIS ST 90066
Certificate Information: 12561 W INDIANAPOLIS ST 90066
- Application / Permit
- 25014-20000-02676
- Plan Check / Job No.
- B25VN16623
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW ADDITION TO THE EXISTING DETACHED GARAGE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 7/3/2025
- Issuing Office
- Current Status
- CofO Issued on 10/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2025 | MADISON ODELL |
| Corrections Issued | 6/10/2025 | MADISON ODELL |
| Plan Check Approved | 7/3/2025 | ALEC MOUSAKHANIAN |
| Issued | 7/3/2025 | APPLICANT |
| CofO in Progress | 10/1/2025 | WILBER ROSALES |
| Permit Finaled | 10/10/2025 | RICHARD STEINBACH |
| CofO Issued | 10/10/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/10/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2025 | JESUS CISNEROS |
| Roof/Waste drainage to street | Cleared | 6/12/2025 | MICHAEL BROWN |
| Grading Pre-Inspection | Cleared | 6/16/2025 | LANNY MERRICK |
| Construction near power lines | Cleared | 6/30/2025 | ENRIQUE ACOSTA |
| Specific Plan | Cleared | 7/1/2025 | EDER ROMERO |
Contact Information
| Contractor | Aldan Construction & Remodeling Inc; Lic. No.: 1030243-B | 8549 WILSHIRE BLVD #1458 BEVERLY HILLS, CA 90211 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/29/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 8/15/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Rough | 8/15/2025 | Approved | WILBER ROSALES |
| PLUMBING-Rough | 8/15/2025 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 8/22/2025 | Approved | MICHAEL ALLEN |
| Insulation | 8/27/2025 | Approved | WILBER ROSALES |
| Drywall Nailing | 9/2/2025 | Approved | WILBER ROSALES |
| Final | 9/22/2025 | Corrections Issued | WILBER ROSALES |
| Footing/Foundation/Slab | 9/22/2025 | Approved | WILBER ROSALES |
| Smoke Detectors | 9/22/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Final | 9/30/2025 | Approved | WILBER ROSALES |
| Final | 9/30/2025 | OK to Issue CofO | WILBER ROSALES |
| HVAC-Final | 9/30/2025 | Approved | WILBER ROSALES |
| PLUMBING-Final | 9/30/2025 | Approved | WILBER ROSALES |