11730 W KITTRIDGE ST 91335

Certificate Information: 11730 W KITTRIDGE ST 91335

Application / Permit
25014-20000-02657
Plan Check / Job No.
B25VN16506
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 27'-10" X 22'-1" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ON SECOND FLOOR OF EXISTING GARAGE (GARAGE TO REMAIN); ADD 4' X 8'-3" LAUNDRY ROOM ON FIRST FLOOR
Permit Issued
Issued on 12/18/2025
Issuing Office
West Los Angeles
Current Status
Issued on 12/18/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/10/2025 APPLICANT
Assigned to Plan Check Engineer 6/26/2025 SELLA BENYAMIN
Corrections Issued 7/2/2025 SELLA BENYAMIN
Quality Review Completed 7/3/2025 STEVEN KIM
Building Plans Picked Up 7/9/2025 APPLICANT
Plan Check Approved 12/18/2025 SELLA BENYAMIN
Issued 12/18/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/16/2025 MICHAEL BROWN
Construction near power lines Cleared 8/26/2025 GEVORK KARAPETYAN
Eng Process Fee Ord 176,300 Cleared 9/2/2025 MICHAEL BROWN
Sewer availability Cleared 9/2/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 12/10/2025 MICHAEL BROWN

Contact Information

Contractor Owner-Builder       ,
Engineer Manoukian,, Krikor Kerop; Lic. No.: C87010 2310 W MAGNOLIA BLVD STE A      BURBANK, CA 91506

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/2/2026 Partial Approval JUAN ALVARADO
Final 4/2/2026 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 4/2/2026 Approved DAVID SCANTLIN
Gas Test 4/2/2026 Approved DAVID SCANTLIN
PLUMBING-Rough 4/2/2026 Partial Approval DAVID SCANTLIN
Sewer 4/2/2026 Approved DAVID SCANTLIN
Underground Mechanical 4/2/2026 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 4/15/2026 Partial Approval JUAN ALVARADO
Wood Frame 4/15/2026 Partial Approval JUAN ALVARADO
Deputy Wood Construction 4/30/2026 Approved ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 4/30/2026 Partial Approval ROBERT GOLD
Pre-Inspection 5/29/2026 Partial Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 6/18/2026 Corrections Issued JUAN ALVARADO
HVAC-Rough 6/18/2026 Not Ready for Inspection JUAN ALVARADO
PLUMBING-Rough 6/18/2026 Approved JUAN ALVARADO
BUILDING-Rough-Frame 7/1/2026 Partial Approval JUAN ALVARADO
ELECTRICAL-Rough 7/1/2026 Approved JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 7/1/2026 Approved JUAN ALVARADO
Green Building Rough 7/1/2026 Not Ready for Inspection JUAN ALVARADO
HVAC-Rough 7/1/2026 Approved JUAN ALVARADO
Interior/Exterior Lathing 7/7/2026 Not Ready for Inspection JUAN ALVARADO
BUILDING-Rough-Frame 7/8/2026 Conditional Approval JUAN ALVARADO
Green Building Rough 7/8/2026 Approved JUAN ALVARADO
Interior/Exterior Lathing 7/8/2026 Approved JUAN ALVARADO
Pre-Inspection 7/8/2026 Corrections Issued JUAN ALVARADO
BUILDING-Rough-Frame 7/20/2026 Approved JUAN ALVARADO
Insulation 7/20/2026 Corrections Issued JUAN ALVARADO