14006-14008 W VALERIO ST 91405

Certificate Information: 14006-14008 W VALERIO ST 91405

Application / Permit
25014-20000-02646
Plan Check / Job No.
B25VN16452
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD TO AND CONVERT (E) ATTACHED TWO CAR GARAGE TO ACCESSOWY DWELLING UNIT AS PER LAMC 12.22 A.33 (c) and (e) ALL WORK PER ENGINEERING
Permit Issued
Issued on 6/26/2025
Issuing Office
Current Status
Issued on 6/26/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/9/2025 APPLICANT
Assigned to Plan Check Engineer 6/12/2025 RARES BODEA
Corrections Issued 6/17/2025 RARES BODEA
Quality Review Completed 6/18/2025 STEVEN KIM
Building Plans Picked Up 6/18/2025 APPLICANT
Plan Check Approved 6/26/2025 RARES BODEA
Issued 6/26/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/20/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 6/20/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 6/20/2025 SAFA JAVANMARDI
Sewer availability Cleared 6/20/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/24/2025 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 7/29/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 7/29/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 8/5/2025 Partial Approval VINCENT HANLEY
Deputy Wood Construction 8/11/2025 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 8/11/2025 Approved DAVID ANDERSON
ELECTRICAL-Rough 8/19/2025 Approved DAVID MATSON
HVAC-Rough 8/19/2025 Corrections Issued DAVID MATSON
PLUMBING-Rough 8/19/2025 Approved DAVID MATSON
Shower Pan 8/19/2025 Approved DAVID MATSON
Wood Frame 8/19/2025 Corrections Issued DAVID MATSON
Insulation 8/25/2025 Conditional Approval MATTHEW NELSON
BUILDING-Rough-Frame 8/28/2025 Approved VINCENT HANLEY
Drywall Nailing 8/28/2025 Approved VINCENT HANLEY
Green Building Rough 8/28/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/28/2025 Partial Approval VINCENT HANLEY
ELECTRICAL-Final 11/7/2025 Approved VINCENT HANLEY
Final 11/7/2025 Not Ready for Inspection VINCENT HANLEY
Green Building Final 11/7/2025 Approved VINCENT HANLEY
HVAC-Final 11/7/2025 Approved VINCENT HANLEY
PLUMBING-Final 11/7/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 11/7/2025 SGSOV Approved VINCENT HANLEY
Service/Power Release 11/7/2025 Approved VINCENT HANLEY
Smoke Detectors 11/7/2025 Approved VINCENT HANLEY