10838 1/2 W STRATHERN ST 91352

Certificate Information: 10838 1/2 W STRATHERN ST 91352

Application / Permit
25014-20000-02607
Plan Check / Job No.
B25VN16146
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE WITH ADDITION TO A (N) 1-STORY ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 66323(a)(2) PER WFPP
Permit Issued
Issued on 8/18/2025
Issuing Office
Current Status
CofO Issued on 3/18/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/5/2025 APPLICANT
Assigned to Plan Check Engineer 6/12/2025 ALFRED RAMIREZ
Corrections Issued 6/14/2025 ALFRED RAMIREZ
Quality Review Completed 6/17/2025 STEVEN KIM
Building Plans Picked Up 7/22/2025 APPLICANT
Applicant returned to address corrections 8/4/2025 ALFRED RAMIREZ
Plan Check Approved 8/18/2025 ALFRED RAMIREZ
Issued 8/18/2025 APPLICANT
CofO in Progress 1/23/2026 MATTHEW NELSON
Permit Finaled 3/18/2026 RUBEN SALAS
CofO Issued 3/18/2026 RUBEN SALAS
Permit Finaled 3/18/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/18/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/18/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 6/18/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/18/2025 LEE GUILBEAUX
Private sewage disp. approval Cleared 8/4/2025 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/29/2025 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 9/5/2025 Corrections Issued MATTHEW NELSON
Special/Order Compliance 9/5/2025 Partial Inspection DAVID MATSON
PLUMBING-Rough 9/11/2025 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 9/15/2025 Approved MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 10/3/2025 Approved DAVID MATSON
HVAC-Rough 10/3/2025 Corrections Issued DAVID MATSON
Insulation 10/3/2025 Partial Approval DAVID MATSON
Wood Frame 10/3/2025 Partial Approval DAVID MATSON
BUILDING-Rough-Frame 10/14/2025 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 10/14/2025 Approved MATTHEW NELSON
HVAC-Rough 10/14/2025 Approved MATTHEW NELSON
Insulation 10/20/2025 Corrections Issued MATTHEW NELSON
Interior/Exterior Lathing 10/20/2025 Partial Approval MATTHEW NELSON
Shower Pan 10/20/2025 Approved MATTHEW NELSON
Insulation 10/24/2025 Approved LOUIS ESCOTO
Drywall Nailing 10/28/2025 Approved MATTHEW NELSON
Green Building Rough 10/28/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 11/18/2025 Partial Approval STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 12/30/2025 SGSOV Not Ready MATTHEW NELSON
BUILDING-Rough-Frame 1/5/2026 Approved MATTHEW NELSON
Final 1/5/2026 Corrections Issued MATTHEW NELSON
Green Building Final 1/5/2026 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 1/5/2026 SGSOV Approved MATTHEW NELSON
Smoke Detectors 1/5/2026 Approved MATTHEW NELSON
Special/Order Compliance 1/5/2026 Not Ready for Inspection MATTHEW NELSON
Final 1/22/2026 Corrections Issued MATTHEW NELSON
Final 1/23/2026 OK to Issue CofO MATTHEW NELSON
Service/Power Release 1/23/2026 Approved MATTHEW NELSON