10838 1/2 W STRATHERN ST 91352
Certificate Information: 10838 1/2 W STRATHERN ST 91352
- Application / Permit
- 25014-20000-02607
- Plan Check / Job No.
- B25VN16146
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE WITH ADDITION TO A (N) 1-STORY ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 66323(a)(2) PER WFPP
- Permit Issued
- Issued on 8/18/2025
- Issuing Office
- Current Status
- CofO Issued on 3/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2025 | ALFRED RAMIREZ |
| Corrections Issued | 6/14/2025 | ALFRED RAMIREZ |
| Quality Review Completed | 6/17/2025 | STEVEN KIM |
| Building Plans Picked Up | 7/22/2025 | APPLICANT |
| Applicant returned to address corrections | 8/4/2025 | ALFRED RAMIREZ |
| Plan Check Approved | 8/18/2025 | ALFRED RAMIREZ |
| Issued | 8/18/2025 | APPLICANT |
| CofO in Progress | 1/23/2026 | MATTHEW NELSON |
| Permit Finaled | 3/18/2026 | RUBEN SALAS |
| CofO Issued | 3/18/2026 | RUBEN SALAS |
| Permit Finaled | 3/18/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/18/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 6/18/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 6/18/2025 | LEE GUILBEAUX |
| Private sewage disp. approval | Cleared | 8/4/2025 | MICHAEL TEMPLE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/29/2025 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 9/5/2025 | Corrections Issued | MATTHEW NELSON |
| Special/Order Compliance | 9/5/2025 | Partial Inspection | DAVID MATSON |
| PLUMBING-Rough | 9/11/2025 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 9/15/2025 | Approved | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 10/3/2025 | Approved | DAVID MATSON |
| HVAC-Rough | 10/3/2025 | Corrections Issued | DAVID MATSON |
| Insulation | 10/3/2025 | Partial Approval | DAVID MATSON |
| Wood Frame | 10/3/2025 | Partial Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 10/14/2025 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 10/14/2025 | Approved | MATTHEW NELSON |
| HVAC-Rough | 10/14/2025 | Approved | MATTHEW NELSON |
| Insulation | 10/20/2025 | Corrections Issued | MATTHEW NELSON |
| Interior/Exterior Lathing | 10/20/2025 | Partial Approval | MATTHEW NELSON |
| Shower Pan | 10/20/2025 | Approved | MATTHEW NELSON |
| Insulation | 10/24/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 10/28/2025 | Approved | MATTHEW NELSON |
| Green Building Rough | 10/28/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 11/18/2025 | Partial Approval | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 12/30/2025 | SGSOV Not Ready | MATTHEW NELSON |
| BUILDING-Rough-Frame | 1/5/2026 | Approved | MATTHEW NELSON |
| Final | 1/5/2026 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 1/5/2026 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/5/2026 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 1/5/2026 | Approved | MATTHEW NELSON |
| Special/Order Compliance | 1/5/2026 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 1/22/2026 | Corrections Issued | MATTHEW NELSON |
| Final | 1/23/2026 | OK to Issue CofO | MATTHEW NELSON |
| Service/Power Release | 1/23/2026 | Approved | MATTHEW NELSON |