14235 W BURTON ST 91402

Certificate Information: 14235 W BURTON ST 91402

Application / Permit
25014-20000-02541
Plan Check / Job No.
B25VN15725
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE FRONT COVERED PORCH. ADDITION TO ENLARGE AND REMODEL KITCHEN. ADDITION TO REAR SFD FOR TWO NEW BEDROOMS, BATHROOM, AND TWO PATIO COVERS.
Permit Issued
Issued on 7/9/2025
Issuing Office
Valley
Current Status
CofO Issued on 2/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2025 APPLICANT
Assigned to Plan Check Engineer 6/6/2025 JEROME MAGAT PALMA
Corrections Issued 6/7/2025 JEROME MAGAT PALMA
Building Plans Picked Up 6/16/2025 APPLICANT
Plan Check Approved 7/8/2025 ALEC MOUSAKHANIAN
Plan Check Approved 7/8/2025 ALEC MOUSAKHANIAN
Issued 7/9/2025 APPLICANT
CofO in Progress 1/29/2026 VINCENT HANLEY
Permit Finaled 2/10/2026 RUBEN SALAS
CofO Issued 2/10/2026 RUBEN SALAS
Permit Finaled 2/10/2026 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/1/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 7/1/2025 RYAN CASTRO
Sewer availability Cleared 7/1/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Shagirian,, Ashot; Lic. No.: C79415 11337 RUNNYMEDE ST      SUN VALLEY, CA 91352

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/12/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 8/14/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 8/14/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 8/22/2025 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 8/22/2025 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 10/3/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Corrections Issued VINCENT HANLEY
HVAC-Rough 10/3/2025 Approved VINCENT HANLEY
PLUMBING-Rough 10/3/2025 Approved VINCENT HANLEY
Deputy Wood Construction 10/7/2025 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 10/8/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/8/2025 Approved VINCENT HANLEY
Green Building Rough 10/8/2025 Approved VINCENT HANLEY
Shower Pan 10/8/2025 Approved VINCENT HANLEY
Insulation 10/16/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 10/16/2025 Approved LOUIS ESCOTO
Drywall Nailing 10/24/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Final 1/23/2026 Approved VINCENT HANLEY
Final 1/23/2026 Corrections Issued VINCENT HANLEY
Green Building Final 1/23/2026 Approved VINCENT HANLEY
HVAC-Final 1/23/2026 Approved VINCENT HANLEY
PLUMBING-Final 1/23/2026 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 1/23/2026 SGSOV Approved VINCENT HANLEY
Smoke Detectors 1/23/2026 Approved VINCENT HANLEY
Final 1/28/2026 OK to Issue CofO VINCENT HANLEY