4916 N LEDGE AVE 91601
Certificate Information: 4916 N LEDGE AVE 91601
- Application / Permit
- 25014-20000-02514
- Plan Check / Job No.
- B25VN15528
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO LIVING ROOM TO FRONT OF (E) SFD, ALL WORK PER ENG.
- Permit Issued
- Issued on 7/17/2025
- Issuing Office
- Valley
- Current Status
- Issued on 7/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2025 | JESSE ARELLANO |
| Corrections Issued | 6/5/2025 | JESSE ARELLANO |
| Building Plans Picked Up | 6/10/2025 | APPLICANT |
| Applicant returned to address corrections | 7/10/2025 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 7/11/2025 | JESSE ARELLANO |
| Applicant returned to address corrections | 7/16/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 7/17/2025 | LUISANGEL VALENZUELA |
| Issued | 7/17/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/18/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 6/18/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Reliable Construction Specialists Inc; Lic. No.: 1024126-B | 10028 BORDEAUX AVE ARLETA, CA 91331 |
| Engineer | Banning,, George Kwame; Lic. No.: C53074 | 7550 LILY COURT FONTANA, CA 92336 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/31/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 8/4/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2025 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2025 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 11/3/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 11/3/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 11/3/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 11/3/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 11/7/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 11/7/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 11/7/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 11/12/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 11/12/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 11/12/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 11/14/2025 | Approved | ROBERTO PALACIOS-LOPEZ |