7444-7446 N ROYER AVE 91307
Certificate Information: 7444-7446 N ROYER AVE 91307
- Application / Permit
- 25014-20000-02509
- Plan Check / Job No.
- B25VN15500
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ADDITION TO (E) ATTACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1), REMODEL AND (N) ADDITION TO (E) SFD.
- Permit Issued
- Issued on 6/27/2025
- Issuing Office
- Current Status
- CofO Issued on 2/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 6/9/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/9/2025 | APPLICANT |
| Plan Check Approved | 6/25/2025 | ISIS ARGUETA |
| Plan Check Approved | 6/25/2025 | ISIS ARGUETA |
| Plan Check Approved | 6/25/2025 | ISIS ARGUETA |
| Issued | 6/27/2025 | APPLICANT |
| CofO in Progress | 1/29/2026 | JEFFREY HARTLINE |
| Permit Finaled | 2/5/2026 | JOHN JANSON |
| CofO Issued | 2/5/2026 | JOHN JANSON |
| Permit Finaled | 2/5/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/11/2025 | DERRICK MAGEE |
| Roof/Waste drainage to street | Cleared | 6/11/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 6/12/2025 | DERRICK MAGEE |
| Construction near power lines | Cleared | 6/23/2025 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/23/2025 | Partial Approval | JEFFREY HARTLINE |
| Deputy Drilled-In Anchors | 7/30/2025 | Conditional Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 7/30/2025 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 7/30/2025 | Conditional Approval | CHRIS CHRISTENSEN |
| Underground Mechanical | 7/30/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Underground Mechanical | 8/7/2025 | Approved | JEFFREY HARTLINE |
| Sewer | 8/14/2025 | Approved | JEFFREY HARTLINE |
| Deputy Drilled-In Anchors | 9/5/2025 | Conditional Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2025 | Partial Approval | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2025 | Partial Approval | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 10/20/2025 | Corrections Issued | JEFFREY HARTLINE |
| Gas Test | 10/20/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 10/20/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 10/20/2025 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 10/20/2025 | Corrections Issued | JEFFREY HARTLINE |
| Wood Frame | 10/20/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 10/27/2025 | Approved | JEFFREY HARTLINE |
| Gas Test | 10/27/2025 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 10/27/2025 | Approved | JEFFREY HARTLINE |
| Rough-Elec/Plmb/HVAC | 10/27/2025 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 10/27/2025 | Approved | JEFFREY HARTLINE |
| Insulation | 11/3/2025 | Approved | JEFFREY HARTLINE |
| Shower Pan | 11/3/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 11/7/2025 | Corrections Issued | HENRY KIM |
| Interior/Exterior Lathing | 11/17/2025 | Partial Approval | JEFFREY HARTLINE |
| Service/Power Release | 12/8/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| PLUMBING-Final | 12/31/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Drywall Nailing | 1/21/2026 | Approved | JEFFREY HARTLINE |
| Final | 1/21/2026 | Corrections Issued | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 1/21/2026 | Approved | JEFFREY HARTLINE |
| Green Building Final | 1/21/2026 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 1/21/2026 | SGSOV Approved | JEFFREY HARTLINE |
| Smoke Detectors | 1/21/2026 | Approved | JEFFREY HARTLINE |
| Final | 1/29/2026 | OK to Issue CofO | JEFFREY HARTLINE |
| Service/Power Release | 1/29/2026 | Approved | JEFFREY HARTLINE |