19420 W BILMOOR PL 91356
Certificate Information: 19420 W BILMOOR PL 91356
- Application / Permit
- 25014-20000-02508
- Plan Check / Job No.
- B25VN15497
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, 21'-0" X 20'-0" ADDITION TO (E) SFD PER ENGINEERING.
- Permit Issued
- Issued on 8/1/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 6/9/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/9/2025 | APPLICANT |
| Issued | 8/1/2025 | APPLICANT |
| CofO in Progress | 2/27/2026 | JOHN KIDWELL |
| Permit Finaled | 3/3/2026 | JOHN JANSON |
| CofO Issued | 3/3/2026 | JOHN JANSON |
| Permit Finaled | 3/3/2026 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/2/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 7/2/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2025 | SAFA JAVANMARDI |
| ZA Case | Cleared | 7/23/2025 | JASON CHAN |
| Grading Pre-Inspection | Cleared | 8/1/2025 | ALEXANDER HELFER |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/12/2025 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 8/14/2025 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2025 | Partial Approval | JOHN KIDWELL |
| Wood Frame | 8/22/2025 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2025 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 9/26/2025 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 9/26/2025 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 10/14/2025 | Partial Approval | JOHN KIDWELL |
| HVAC-Rough | 10/22/2025 | Corrections Issued | SCOTT SOBEL |
| Insulation | 10/22/2025 | Corrections Issued | SCOTT SOBEL |
| BUILDING-Rough-Frame | 10/24/2025 | Approved | JOHN KIDWELL |
| Green Building Rough | 10/24/2025 | Approved | JOHN KIDWELL |
| HVAC-Rough | 10/24/2025 | Approved | JOHN KIDWELL |
| Insulation | 10/24/2025 | Approved | JOHN KIDWELL |
| Drywall Nailing | 11/4/2025 | Approved | JOHN KIDWELL |
| Shower Pan | 11/4/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Shower Pan | 11/10/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 11/14/2025 | Partial Approval | JOHN KIDWELL |
| Final | 2/12/2026 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 2/12/2026 | Approved | JOHN KIDWELL |
| Green Building Final | 2/12/2026 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 2/12/2026 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 2/12/2026 | Approved | JOHN KIDWELL |
| Final | 2/27/2026 | OK to Issue CofO | JOHN KIDWELL |
| Green Building Final | 2/27/2026 | Approved | JOHN KIDWELL |