18001 W BORIS DR 91316

Certificate Information: 18001 W BORIS DR 91316

Application / Permit
25014-20000-02502
Plan Check / Job No.
B25VN15483
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADDITION TO CREATE 1-STORY (101'-2" X 44'-6.75" IRR SHAPE) SINGLE FAMILY DWELLING WITH ATTACHED PATIO COVER. NFPA 13D FIRE SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 9/25/2025
Issuing Office
Current Status
CofO in Progress on 6/4/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/30/2025 APPLICANT
Assigned to Plan Check Engineer 6/5/2025 VAHAN JIVALAGIAN
Corrections Issued 6/13/2025 VAHAN JIVALAGIAN
Quality Review Completed 6/18/2025 OMID HEDAYAT
Applicant returned to address corrections 8/19/2025 VAHAN JIVALAGIAN
Building Plans Picked Up 9/16/2025 APPLICANT
Plan Check Approved 9/24/2025 VAHAN JIVALAGIAN
Issued 9/25/2025 APPLICANT
CofO in Progress 6/4/2026 JOHN KIDWELL

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 6/28/2025 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 6/28/2025 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 6/28/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/28/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 6/28/2025 LEE GUILBEAUX
Sewer availability Cleared 6/28/2025 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 7/3/2025 LEE GUILBEAUX
Hydrant and Access approval Cleared 8/11/2025 GILBERT URREA
GPI Written Notices Cleared 8/14/2025 VAHAN JIVALAGIAN
Grading Pre-Inspection Cleared 8/14/2025 VAHAN JIVALAGIAN

Contact Information

Contractor Sharp Builders Inc; Lic. No.: 1078848-B 8432 SHARP AVE      SUN VALLEY, CA 91352
Engineer Asprer,, Anjero; Lic. No.: C91126 2708 FOOTHILL BLVD. #1006      LA CRESCENTA, CA 91214

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/29/2025 Partial Approval JOHN KIDWELL
Underground Mechanical 9/29/2025 Partial Approval JOHN KIDWELL
Deputy Drilled-In Anchors 10/1/2025 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 12/8/2025 Partial Approval JOHN KIDWELL
Green Building Rough 12/8/2025 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 12/8/2025 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 12/8/2025 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 12/11/2025 Approved JOHN KIDWELL
Shower Pan 12/11/2025 Approved JOHN KIDWELL
BUILDING-Rough-Frame 12/24/2025 Partial Inspection JOHN KIDWELL
Green Building Rough 12/24/2025 Approved JOHN KIDWELL
HVAC-Rough 12/24/2025 Not Ready for Inspection JOHN KIDWELL
Insulation 12/24/2025 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 12/24/2025 Partial Approval JOHN KIDWELL
Verify Sprinkler Sign Off 12/24/2025 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 12/30/2025 Approved JOHN KIDWELL
Drywall Nailing 12/30/2025 Approved JOHN KIDWELL
Insulation 12/30/2025 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 12/30/2025 Approved JOHN KIDWELL
Final 4/22/2026 Corrections Issued JOHN KIDWELL
Footing/Foundation/Slab 4/22/2026 Approved JOHN KIDWELL
Green Building Final 4/22/2026 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 4/22/2026 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 4/22/2026 Approved JOHN KIDWELL
Final 5/6/2026 Corrections Issued JOHN KIDWELL
Green Building Final 5/6/2026 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 5/6/2026 SGSOV Approved JOHN KIDWELL
Final 6/3/2026 OK to Issue CofO JOHN KIDWELL
Green Building Final 6/3/2026 Approved JOHN KIDWELL