8107 N LAURELGROVE AVE 91605

Certificate Information: 8107 N LAURELGROVE AVE 91605

Application / Permit
25014-20000-02497
Plan Check / Job No.
B25VN15470
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL TO (E) SFD WITH ADDITIONS TO CREATE A 1-STORY 60'-0" x 41'--7" SINGLE FAMILY DWELLING UNIT WITH ATTACHED TRELLISS PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
Permit Issued
Issued on 7/21/2025
Issuing Office
Valley
Current Status
CofO Issued on 4/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2025 APPLICANT
Assigned to Plan Check Engineer 6/18/2025 ALFRED RAMIREZ
Corrections Issued 6/24/2025 ALFRED RAMIREZ
Quality Review Completed 6/26/2025 STEVEN KIM
Building Plans Picked Up 6/27/2025 APPLICANT
Applicant returned to address corrections 7/15/2025 ALFRED RAMIREZ
Plan Check Approved 7/21/2025 ALFRED RAMIREZ
Issued 7/21/2025 APPLICANT
CofO in Progress 3/19/2026 MATTHEW NELSON
CofO Issued 4/21/2026 RUBEN SALAS
Permit Finaled 4/21/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/26/2025 RYAN CASTRO
Sewer availability Cleared 6/26/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/27/2025 DERRICK MAGEE

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/4/2025 Partial Approval MATTHEW NELSON
PLUMBING-Rough 8/4/2025 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 8/7/2025 Approved MATTHEW NELSON
BUILDING-Rough-Frame 8/15/2025 Partial Approval MATTHEW NELSON
PLUMBING-Rough 8/15/2025 Partial Approval MATTHEW NELSON
Deputy Wood Construction 8/19/2025 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 8/19/2025 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 9/16/2025 Partial Approval MATTHEW NELSON
PLUMBING-Rough 9/16/2025 Approved MATTHEW NELSON
HVAC-Rough 10/2/2025 Approved MATTHEW NELSON
Shower Pan 10/2/2025 Approved MATTHEW NELSON
BUILDING-Rough-Frame 10/6/2025 Approved MATTHEW NELSON
ELECTRICAL-Rough 10/6/2025 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 10/6/2025 Approved MATTHEW NELSON
Green Building Rough 10/6/2025 Approved MATTHEW NELSON
Insulation 10/14/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 10/14/2025 Approved MATTHEW NELSON
Drywall Nailing 10/17/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 10/22/2025 Approved MATTHEW NELSON
PLUMBING-Rough 11/12/2025 Approved MATTHEW NELSON
ELECTRICAL-Final 2/18/2026 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Final 2/18/2026 Approved MATTHEW NELSON
Final 3/13/2026 Corrections Issued DAVID MATSON
Green Building Final 3/13/2026 Approved DAVID MATSON
SGSOV-Seismic Gas S/O Valve 3/13/2026 SGSOV Approved DAVID MATSON
Smoke Detectors 3/13/2026 Approved DAVID MATSON
Final 3/18/2026 OK to Issue CofO MATTHEW NELSON