4552 W RUSSELL AVE 90027

Certificate Information: 4552 W RUSSELL AVE 90027

Application / Permit
25014-20000-02487
Plan Check / Job No.
B25VN15412
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE AND NEW ADDITION TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1). WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 6/27/2025
Issuing Office
Current Status
CofO Issued on 4/7/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2025 APPLICANT
Assigned to Plan Check Engineer 6/4/2025 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 6/10/2025 SEWADA ZADOORIAN MILAGARDI
Building Plans Picked Up 6/10/2025 APPLICANT
Applicant returned to address corrections 6/17/2025 ALEC MOUSAKHANIAN
Applicant returned to address corrections 6/26/2025 ALEC MOUSAKHANIAN
Issued 6/27/2025 APPLICANT
CofO in Progress 4/6/2026 ENRIQUE MIRELES
Permit Finaled 4/7/2026 DEROLD HAUFF
CofO Issued 4/7/2026 DEROLD HAUFF
Permit Finaled 4/7/2026 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 6/10/2025 JASON CHAN
Address approval Cleared 6/14/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 6/14/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/14/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/15/2025 LEE GUILBEAUX
Sewer availability Cleared 6/15/2025 LEE GUILBEAUX
Grading Pre-Inspection Cleared 6/18/2025 ALEXANDER HELFER
Construction near power lines Cleared 6/23/2025 ENRIQUE ACOSTA
Specific Plan Cleared 6/24/2025 YAMILLET BRIZUELA
GPI Written Notices Cleared 6/26/2025 SEWADA ZADOORAN MILAGARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Abedian,, Vanik; Lic. No.: S5323 2906 JOLLEY DR      BURBANK, CA 91504

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/5/2025 Approved ENRIQUE MIRELES
Sewer 9/17/2025 Approved ENRIQUE MIRELES
Deputy Wood Construction 9/23/2025 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 9/29/2025 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/9/2025 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/16/2025 Approved ENRIQUE MIRELES
Deputy Wood Construction 11/12/2025 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 11/24/2025 Partial Approval JEFFREY MEAD
BUILDING-Rough-Frame 12/16/2025 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 12/16/2025 Approved ENRIQUE MIRELES
Green Building Rough 12/16/2025 Approved ENRIQUE MIRELES
HVAC-Rough 12/16/2025 Approved ENRIQUE MIRELES
PLUMBING-Rough 12/16/2025 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 12/16/2025 Approved ENRIQUE MIRELES
Insulation 12/26/2025 Approved ALEX COLIN
Interior/Exterior Lathing 12/26/2025 Partial Approval ALEX COLIN
Drywall Nailing 12/30/2025 Approved ENRIQUE MIRELES
Shower Pan 1/12/2026 Approved ENRIQUE MIRELES
Final 3/27/2026 Corrections Issued ENRIQUE MIRELES
Green Building Final 3/27/2026 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 3/27/2026 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 3/27/2026 Approved ENRIQUE MIRELES
Final 4/3/2026 OK to Issue CofO ENRIQUE MIRELES