7889 N OSTROM AVE 91406

Certificate Information: 7889 N OSTROM AVE 91406

Application / Permit
25014-20000-02459
Plan Check / Job No.
B25VN15245
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 13' X 15' TO AND CONVERT (E) DET. GARAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(2) ALL WORK PER WFPP SEE COMMENTS
Permit Issued
Issued on 7/21/2025
Issuing Office
Current Status
CofO Issued on 3/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/29/2025 APPLICANT
Assigned to Plan Check Engineer 6/4/2025 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 6/10/2025 SEWADA ZADOORIAN MILAGARDI
Building Plans Picked Up 6/10/2025 APPLICANT
Plan Check Approved 7/21/2025 ANGELICA MARTINEZ
Issued 7/21/2025 APPLICANT
CofO in Progress 2/9/2026 GAREN HAYRAPETYAN
Permit Finaled 3/3/2026 RUBEN SALAS
CofO Issued 3/3/2026 RUBEN SALAS
Permit Finaled 3/3/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/11/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/11/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 6/11/2025 RYAN CASTRO
Sewer availability Cleared 6/11/2025 RYAN CASTRO
Construction near power lines Cleared 7/21/2025 ENRIQUE ACOSTA
Construction within easement Cleared 7/21/2025 ENRIQUE ACOSTA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 10/16/2025 Partial Approval GAREN HAYRAPETYAN
Underground Mechanical 10/16/2025 Approved GAREN HAYRAPETYAN
Deputy Drilled-In Anchors 10/21/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 10/21/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 11/7/2025 Corrections Issued GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 11/7/2025 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 11/7/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 11/7/2025 Conditional Approval GAREN HAYRAPETYAN
BUILDING-Rough-Frame 11/14/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 11/14/2025 Approved GAREN HAYRAPETYAN
Gas Test 11/14/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 11/14/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 11/14/2025 Partial Approval GAREN HAYRAPETYAN
Insulation 11/20/2025 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 11/25/2025 Approved CHRISTOPHER MORFIN
Shower Pan 11/25/2025 Approved CHRISTOPHER MORFIN
Interior/Exterior Lathing 12/1/2025 Partial Approval JACK KARGODORIAN
Final 2/4/2026 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 2/4/2026 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 2/4/2026 SGSOV Approved GAREN HAYRAPETYAN
Sewer 2/4/2026 Approved GAREN HAYRAPETYAN
Smoke Detectors 2/4/2026 Approved GAREN HAYRAPETYAN
Final 2/9/2026 OK to Issue CofO GAREN HAYRAPETYAN
Service/Power Release 2/9/2026 Approved GAREN HAYRAPETYAN