1434 S OGDEN DR 90019
Certificate Information: 1434 S OGDEN DR 90019
- Application / Permit
- 25014-20000-02429
- Plan Check / Job No.
- B25VN15080
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED IRREGULAR SHAPED 2-STORY ADDITION AND REMODEL TO (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/18/2025
- Issuing Office
- Current Status
- Issued on 8/18/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2025 | RAPHAEL ROSAS |
| Corrections Issued | 6/10/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 6/10/2025 | STEVEN KIM |
| Building Plans Picked Up | 6/16/2025 | APPLICANT |
| Plan Check Approved | 8/18/2025 | RAPHAEL ROSAS |
| Issued | 8/18/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/21/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 7/9/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Good Life Home Design Inc; Lic. No.: 1094738-B | 630 MASSELIN AVENUE APT 315 LOS ANGELES, CA 90036 |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/22/2025 | Approved | ARTHUR NEGRETE |
| METHANE-Barrier | 9/22/2025 | Approved | ARTHUR NEGRETE |
| METHANE-Subgrade | 9/22/2025 | Approved | ARTHUR NEGRETE |
| Deputy Other (see comments) | 9/30/2025 | Conditional Approval | ALEX COLIN |
| Deputy Drilled-In Anchors | 10/1/2025 | Conditional Approval | ALEX COLIN |
| Special/Order Compliance | 10/1/2025 | Partial Inspection | ALEX COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2025 | Partial Approval | WILLIAM SIERRA |
| PLUMBING-Rough | 10/15/2025 | Partial Approval | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2025 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2025 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Rough | 1/2/2026 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 1/2/2026 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 1/16/2026 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 1/16/2026 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 1/28/2026 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 3/27/2026 | Approved | BRENDAN MORELLI |
| Green Building Rough | 3/27/2026 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 3/27/2026 | Approved | BRENDAN MORELLI |
| METHANE-Rough | 3/27/2026 | Approved | BRENDAN MORELLI |
| Insulation | 4/6/2026 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 4/21/2026 | Approved | ALEX COLIN |
| Shower Pan | 5/7/2026 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 5/13/2026 | Approved | DAVID WILLIAMS |