6710 N RUFFNER AVE 91406
Certificate Information: 6710 N RUFFNER AVE 91406
- Application / Permit
- 25014-20000-02391
- Plan Check / Job No.
- B25VN14851
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REAR ADDITION AND REMODEL TO THE (E) SINGLE FAMILY DWELLING TO EXTEND BEDROOM 2 AND 3.
- Permit Issued
- Issued on 8/7/2025
- Issuing Office
- Current Status
- CofO Issued on 10/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2025 | GIOVANNY CHAVEZ |
| Corrections Issued | 5/31/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 7/25/2025 | ISIS ARGUETA |
| Plan Check Approved | 8/6/2025 | GIOVANNY CHAVEZ |
| Issued | 8/7/2025 | APPLICANT |
| CofO in Progress | 10/6/2025 | GAREN HAYRAPETYAN |
| CofO Issued | 10/7/2025 | RUBEN SALAS |
| Permit Finaled | 10/7/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 7/28/2025 | BIAINA HARITUNIAN |
Contact Information
| Architect | Palka,, Joseph Anthony; Lic. No.: NA24276 | , |
| Contractor | Owner-Builder | , |
| Engineer | Cox,, Steven Jeffrey; Lic. No.: NA48940 | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/14/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 8/14/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 8/15/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Deputy Reinf. Concrete | 8/21/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/21/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 8/21/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Structural Steel Frame | 8/21/2025 | Partial Approval | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 8/25/2025 | Partial Approval | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2025 | Approved | WAYNE REGESTER |
| Insulation | 8/26/2025 | Approved | WAYNE REGESTER |
| Pre-Inspection | 8/26/2025 | Approved | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Rough | 8/27/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Pre-Inspection | 8/27/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Structural Steel Frame | 8/27/2025 | Not Ready for Inspection | WAYNE REGESTER |
| BUILDING-Rough-Frame | 9/4/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Deputy Drilled-In Anchors | 9/4/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Green Building Rough | 9/4/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Pre-Inspection | 9/4/2025 | Partial Inspection | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 9/8/2025 | Partial Approval | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2025 | Approved | WAYNE REGESTER |
| HVAC-Rough | 9/8/2025 | Approved | WAYNE REGESTER |
| Insulation | 9/10/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 9/10/2025 | Approved | WAYNE REGESTER |
| Drywall Nailing | 9/15/2025 | Approved | MISAEL ESPARZA |
| Green Building Rough | 9/15/2025 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/6/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 10/6/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Green Building Final | 10/6/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 10/6/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 10/6/2025 | Approved | GAREN HAYRAPETYAN |
| Structural Steel Frame | 10/6/2025 | Approved | GAREN HAYRAPETYAN |