12227 W EVERGLADE ST 90066

Certificate Information: 12227 W EVERGLADE ST 90066

Application / Permit
25014-20000-02390
Plan Check / Job No.
B25VN14842
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO AN (E) 1-STORY SFD AND STRUCTURAL REMODEL OF THE ENTIRE HOUSE.
Permit Issued
Issued on 6/16/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/27/2025 APPLICANT
Assigned to Plan Check Engineer 5/27/2025 RICHARD GARCIA
Corrections Issued 5/28/2025 RICHARD GARCIA
Building Plans Picked Up 5/30/2025 APPLICANT
Plan Check Approved 6/13/2025 JOHNPAUL ISIP
Issued 6/16/2025 APPLICANT
CofO in Progress 3/11/2026 ARAM AVEDISIAN
Permit Finaled 3/12/2026 RICHARD STEINBACH
CofO Issued 3/12/2026 RICHARD STEINBACH
Permit Finaled 3/12/2026 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/9/2025 LIAM ODONOVAN
Sewer availability Cleared 6/9/2025 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 6/10/2025 LIAM ODONOVAN
Grading Pre-Inspection Cleared 6/10/2025 LANNY MERRICK
Specific Plan Cleared 6/11/2025 RICHARD WOO

Contact Information

Contractor Apex Investment Holdings; Lic. No.: 943202-B 7095 HOLLYWOOD BOULEVARD #1290      LOS ANGELES, CA 90028
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/11/2025 Approved WILBER ROSALES
Excavation/Setback/Form/Re-Bar 7/11/2025 Corrections Issued WILBER ROSALES
Footing/Foundation/Slab 7/11/2025 Corrections Issued WILBER ROSALES
Special/Order Compliance 8/5/2025 Corrections Issued KIRK SANDERS
Underground Mechanical 8/5/2025 Partial Inspection KIRK SANDERS
PLUMBING-Rough 8/8/2025 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/6/2025 Partial Approval KIRK SANDERS
PLUMBING-Rough 10/6/2025 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 10/8/2025 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 10/8/2025 Approved KIRK SANDERS
HVAC-Rough 10/8/2025 Conditional Approval KIRK SANDERS
Special/Order Compliance 10/8/2025 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 10/22/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 10/22/2025 Conditional Approval KIRK SANDERS
HVAC-Rough 10/22/2025 Corrections Issued KIRK SANDERS
PLUMBING-Rough 10/22/2025 Approved KIRK SANDERS
Underground Mechanical 10/22/2025 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 10/28/2025 Approved KIRK SANDERS
Green Building Rough 10/28/2025 Approved KIRK SANDERS
HVAC-Rough 10/28/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 10/28/2025 Partial Approval KIRK SANDERS
Insulation 10/31/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 10/31/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 11/4/2025 Not Ready for Inspection KIRK SANDERS
Shower Pan 11/4/2025 Approved KIRK SANDERS
Drywall Nailing 11/10/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 11/10/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 1/28/2026 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 2/3/2026 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Final 2/10/2026 Approved ARAM AVEDISIAN
Gas Test 2/10/2026 Approved ARAM AVEDISIAN
Service/Power Release 2/10/2026 Approved ARAM AVEDISIAN
Final 3/6/2026 Corrections Issued ARAM AVEDISIAN
Green Building Final 3/6/2026 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 3/6/2026 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 3/6/2026 Approved ARAM AVEDISIAN
Final 3/11/2026 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 3/11/2026 Approved ARAM AVEDISIAN