17409 W MAYFLOWER DR 91344
Certificate Information: 17409 W MAYFLOWER DR 91344
- Application / Permit
- 25014-20000-02382
- Plan Check / Job No.
- B25VN14775
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to Garage and Convert Garage to Living Space. New Carport
- Permit Issued
- Issued on 8/9/2025
- Issuing Office
- Current Status
- CofO in Progress on 6/4/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2025 | SUNMIN LEE |
| Corrections Issued | 6/9/2025 | SUNMIN LEE |
| Applicant returned to address corrections | 7/22/2025 | SUNMIN LEE |
| Applicant returned to address corrections | 7/29/2025 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 8/1/2025 | SUNMIN LEE |
| Plan Check Approved | 8/6/2025 | SUNMIN LEE |
| Issued | 8/9/2025 | APPLICANT |
| CofO in Progress | 5/20/2026 | STEVEN BACK |
| No Progress | 6/4/2026 | CHRISTOPHER WILSON |
| CofO in Progress | 6/4/2026 | CHRISTOPHER WILSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/26/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 6/30/2025 | DERRICK MAGEE |
| GPI Written Notices | Cleared | 7/22/2025 | SUNMIN LEE |
| Grading Pre-Inspection | Cleared | 7/22/2025 | MANUEL TEJADA |
Contact Information
| Contractor | Continental Remodeling Inc; Lic. No.: 1104303-B | , |
| Engineer | Vasquez,, Mario A; Lic. No.: C89006 | 1942 SPANISH BROOM DR PALMDALE, CA 93550 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/13/2025 | Partial Approval | STEVEN BACK |
| Sewer | 8/13/2025 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 8/18/2025 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 8/22/2025 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 8/27/2025 | Not Ready for Inspection | STEVEN BACK |
| Footing/Foundation/Slab | 9/2/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Excavation/Setback/Form/Re-Bar | 9/4/2025 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 9/4/2025 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 9/8/2025 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 10/7/2025 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2025 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 10/7/2025 | Approved | STEVEN BACK |
| PLUMBING-Rough | 10/7/2025 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 10/27/2025 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 10/27/2025 | Approved | STEVEN BACK |
| HVAC-Rough | 10/27/2025 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 10/27/2025 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 11/5/2025 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 11/5/2025 | No Access for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 11/13/2025 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 11/13/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 11/13/2025 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 12/1/2025 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 12/1/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 12/1/2025 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 12/4/2025 | Partial Approval | DAVID SCANTLIN |
| Interior/Exterior Lathing | 12/4/2025 | Partial Approval | DAVID SCANTLIN |
| Insulation | 12/8/2025 | No Access for Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 12/15/2025 | Corrections Issued | STEVEN BACK |
| Insulation | 12/15/2025 | Corrections Issued | STEVEN BACK |
| Drywall Nailing | 12/19/2025 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 12/24/2025 | Approved | STEVEN BACK |
| Drywall Nailing | 12/24/2025 | Approved | STEVEN BACK |
| Insulation | 12/24/2025 | Approved | STEVEN BACK |
| Shower Pan | 1/9/2026 | No Access for Inspection | JEFFREY PARD |
| Interior/Exterior Lathing | 1/13/2026 | Approved | STEVEN BACK |
| Shower Pan | 1/13/2026 | Approved | STEVEN BACK |
| Final | 2/27/2026 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 2/27/2026 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 2/27/2026 | Corrections Issued | STEVEN BACK |
| Final | 3/23/2026 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 3/23/2026 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 3/23/2026 | No Access for Inspection | STEVEN BACK |
| Final | 3/26/2026 | Corrections Issued | STEVEN BACK |
| Smoke Detectors | 3/26/2026 | Approved | STEVEN BACK |
| Final | 4/10/2026 | Corrections Issued | STEVEN BACK |
| Final | 5/20/2026 | OK to Issue CofO | STEVEN BACK |