13415 W CORNELIUS ST 91331

Certificate Information: 13415 W CORNELIUS ST 91331

Application / Permit
25014-20000-02374
Plan Check / Job No.
B25VN14767
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERT (E) DETACHED GARAGE TO ADU PER GC 66323(a)(1)
Permit Issued
Issued on 6/17/2025
Issuing Office
Current Status
CofO Issued on 2/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/28/2025 APPLICANT
Assigned to Plan Check Engineer 5/30/2025 SERGIO MUNIZ
Corrections Issued 5/31/2025 SERGIO MUNIZ
Plan Check Approved 6/16/2025 SERGIO MUNIZ
Issued 6/17/2025 APPLICANT
CofO in Progress 1/2/2026 VINCENT HANLEY
Permit Finaled 2/3/2026 RUBEN SALAS
CofO Issued 2/3/2026 RUBEN SALAS
Permit Finaled 2/3/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/6/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 6/6/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 6/6/2025 SAFA JAVANMARDI
Sewer availability Cleared 6/6/2025 SAFA JAVANMARDI

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor All Stars Builders Inc; Lic. No.: 1090757-B       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/22/2025 Partial Approval RAUL OLAGI
Sewer 7/22/2025 Approved RAUL OLAGI
Underground Mechanical 7/22/2025 Approved RAUL OLAGI
Deputy Drilled-In Anchors 7/29/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 7/30/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 8/26/2025 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 9/11/2025 Approved JOSE AVILA
HVAC-Rough 9/11/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 9/11/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 9/29/2025 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 9/29/2025 Approved KEVIN BERBERYAN
Green Building Rough 9/29/2025 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Rough 9/29/2025 Corrections Issued KEVIN BERBERYAN
MERV13>=Rough 9/29/2025 Approved KEVIN BERBERYAN
Insulation 10/10/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/10/2025 Approved MICHEL ABAJAN
Drywall Nailing 10/17/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/28/2025 Not Ready for Inspection LOUIS ESCOTO
Shower Pan 10/28/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 11/5/2025 Approved MICHEL ABAJAN
Shower Pan 11/5/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 12/10/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 12/10/2025 Corrections Issued MICHEL ABAJAN
Final 12/10/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 12/10/2025 Approved MICHEL ABAJAN
Green Building Rough 12/10/2025 Approved MICHEL ABAJAN
HVAC-Final 12/10/2025 Approved MICHEL ABAJAN
MERV13>=Final 12/10/2025 Approved MICHEL ABAJAN
PLUMBING-Final 12/10/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/10/2025 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 12/10/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 12/18/2025 Approved MICHEL ABAJAN
Final 12/18/2025 Corrections Issued MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/18/2025 SGSOV Approved MICHEL ABAJAN
Final 1/2/2026 OK to Issue CofO VINCENT HANLEY
HVAC-Final 1/2/2026 Approved VINCENT HANLEY
PLUMBING-Final 1/2/2026 Approved VINCENT HANLEY