13415 W CORNELIUS ST 91331
Certificate Information: 13415 W CORNELIUS ST 91331
- Application / Permit
- 25014-20000-02374
- Plan Check / Job No.
- B25VN14767
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVERT (E) DETACHED GARAGE TO ADU PER GC 66323(a)(1)
- Permit Issued
- Issued on 6/17/2025
- Issuing Office
- Current Status
- CofO Issued on 2/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2025 | SERGIO MUNIZ |
| Corrections Issued | 5/31/2025 | SERGIO MUNIZ |
| Plan Check Approved | 6/16/2025 | SERGIO MUNIZ |
| Issued | 6/17/2025 | APPLICANT |
| CofO in Progress | 1/2/2026 | VINCENT HANLEY |
| Permit Finaled | 2/3/2026 | RUBEN SALAS |
| CofO Issued | 2/3/2026 | RUBEN SALAS |
| Permit Finaled | 2/3/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/6/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 6/6/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 6/6/2025 | SAFA JAVANMARDI |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | All Stars Builders Inc; Lic. No.: 1090757-B | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/22/2025 | Partial Approval | RAUL OLAGI |
| Sewer | 7/22/2025 | Approved | RAUL OLAGI |
| Underground Mechanical | 7/22/2025 | Approved | RAUL OLAGI |
| Deputy Drilled-In Anchors | 7/29/2025 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 7/30/2025 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2025 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 9/11/2025 | Approved | JOSE AVILA |
| HVAC-Rough | 9/11/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 9/11/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 9/29/2025 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 9/29/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 9/29/2025 | Corrections Issued | KEVIN BERBERYAN |
| MERV13>=Rough | 9/29/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 10/10/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 10/10/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 10/17/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 10/28/2025 | Not Ready for Inspection | LOUIS ESCOTO |
| Shower Pan | 10/28/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 11/5/2025 | Approved | MICHEL ABAJAN |
| Shower Pan | 11/5/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/10/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 12/10/2025 | Corrections Issued | MICHEL ABAJAN |
| Final | 12/10/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 12/10/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 12/10/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 12/10/2025 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 12/10/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 12/10/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 12/10/2025 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 12/10/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 12/18/2025 | Approved | MICHEL ABAJAN |
| Final | 12/18/2025 | Corrections Issued | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 12/18/2025 | SGSOV Approved | MICHEL ABAJAN |
| Final | 1/2/2026 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 1/2/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 1/2/2026 | Approved | VINCENT HANLEY |