10211 N NASSAU AVE 91040

Certificate Information: 10211 N NASSAU AVE 91040

Application / Permit
25014-20000-02341
Plan Check / Job No.
B25VN14618
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO (E) DETACHED GARAGE AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER 12.22 A.33(c) AND (d)
Permit Issued
Issued on 6/20/2025
Issuing Office
Current Status
Issued on 6/20/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/23/2025 APPLICANT
Assigned to Plan Check Engineer 5/29/2025 SERGIO MUNIZ
Corrections Issued 5/29/2025 SERGIO MUNIZ
Applicant returned to address corrections 6/12/2025 GURUNATH NESARAJAH
Plan Check Approved 6/17/2025 SERGIO MUNIZ
Plan Check Approved 6/18/2025 SERGIO MUNIZ
Issued 6/20/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/3/2025 GERMAN RODRIGUEZ MENDOZA
Address approval Cleared 6/5/2025 TAL SHEMEN
Roof/Waste drainage to street Cleared 6/5/2025 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 6/6/2025 TAL SHEMEN
Sewer availability Cleared 6/6/2025 TAL SHEMEN
Construction near power lines Cleared 6/10/2025 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/26/2026 Partial Approval DAVID ANDERSON
Footing/Foundation/Slab 6/2/2026 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 6/11/2026 Approved DAVID ANDERSON
ELECTRICAL-Rough 6/18/2026 Corrections Issued DAVID ANDERSON
HVAC-Rough 6/18/2026 Partial Approval DAVID ANDERSON
PLUMBING-Rough 6/18/2026 Corrections Issued DAVID ANDERSON
ELECTRICAL-Rough 6/23/2026 Approved DAVID ANDERSON
PLUMBING-Rough 6/23/2026 Approved DAVID ANDERSON
BUILDING-Rough-Frame 6/26/2026 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 6/26/2026 Approved DAVID ANDERSON
Green Building Rough 6/26/2026 Approved DAVID ANDERSON
Insulation 6/29/2026 Corrections Issued DAVID ANDERSON
Interior/Exterior Lathing 6/29/2026 Partial Approval DAVID ANDERSON
Drywall Nailing 7/8/2026 Approved MATTHEW NELSON
Insulation 7/8/2026 Approved MATTHEW NELSON