10211 N NASSAU AVE 91040
Certificate Information: 10211 N NASSAU AVE 91040
- Application / Permit
- 25014-20000-02341
- Plan Check / Job No.
- B25VN14618
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO (E) DETACHED GARAGE AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 6/20/2025
- Issuing Office
- Current Status
- Issued on 6/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/29/2025 | SERGIO MUNIZ |
| Corrections Issued | 5/29/2025 | SERGIO MUNIZ |
| Applicant returned to address corrections | 6/12/2025 | GURUNATH NESARAJAH |
| Plan Check Approved | 6/17/2025 | SERGIO MUNIZ |
| Plan Check Approved | 6/18/2025 | SERGIO MUNIZ |
| Issued | 6/20/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/3/2025 | GERMAN RODRIGUEZ MENDOZA |
| Address approval | Cleared | 6/5/2025 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 6/5/2025 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2025 | TAL SHEMEN |
| Sewer availability | Cleared | 6/6/2025 | TAL SHEMEN |
| Construction near power lines | Cleared | 6/10/2025 | OSCAR CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/26/2026 | Partial Approval | DAVID ANDERSON |
| Footing/Foundation/Slab | 6/2/2026 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2026 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 6/18/2026 | Corrections Issued | DAVID ANDERSON |
| HVAC-Rough | 6/18/2026 | Partial Approval | DAVID ANDERSON |
| PLUMBING-Rough | 6/18/2026 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 6/23/2026 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 6/23/2026 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 6/26/2026 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2026 | Approved | DAVID ANDERSON |
| Green Building Rough | 6/26/2026 | Approved | DAVID ANDERSON |
| Insulation | 6/29/2026 | Corrections Issued | DAVID ANDERSON |
| Interior/Exterior Lathing | 6/29/2026 | Partial Approval | DAVID ANDERSON |
| Drywall Nailing | 7/8/2026 | Approved | MATTHEW NELSON |
| Insulation | 7/8/2026 | Approved | MATTHEW NELSON |