15519 W LEMARSH ST 91345

Certificate Information: 15519 W LEMARSH ST 91345

Application / Permit
25014-20000-02339
Plan Check / Job No.
B25VN14606
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Garage conversion to ADU with addition per state law
Permit Issued
Issued on 9/5/2025
Issuing Office
Current Status
CofO Issued on 4/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2025 APPLICANT
Assigned to Plan Check Engineer 6/6/2025 NEHEMIAS RAMOS
Corrections Issued 6/6/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 8/8/2025 KELVIN CHUONG
Applicant returned to address corrections 8/20/2025 NEHEMIAS RAMOS
Plan Check Approved 9/3/2025 NEHEMIAS RAMOS
Issued 9/5/2025 APPLICANT
CofO in Progress 3/16/2026 JENNIFER RABUCHIN
Permit Finaled 4/2/2026 RUBEN SALAS
CofO Issued 4/2/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/15/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/15/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/2/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 7/2/2025 LEE GUILBEAUX
Sewer availability Cleared 7/2/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/10/2025 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 11/13/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 11/13/2025 Corrections Issued JENNIFER RABUCHIN
Sewer 11/13/2025 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/12/2025 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/23/2025 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 12/23/2025 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/23/2025 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 12/23/2025 Approved JENNIFER RABUCHIN
Green Building Rough 12/23/2025 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 12/23/2025 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/2/2026 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 1/2/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 1/2/2026 Approved JENNIFER RABUCHIN
HVAC-Rough 1/2/2026 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 1/2/2026 Approved JENNIFER RABUCHIN
MERV13>=Rough 1/2/2026 Approved JENNIFER RABUCHIN
PLUMBING-Rough 1/2/2026 Approved JENNIFER RABUCHIN
Insulation 1/7/2026 Approved JENNIFER RABUCHIN
Special/Order Compliance 1/7/2026 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 1/12/2026 Approved MATTHEW NELSON
ELECTRICAL-Final 2/23/2026 Corrections Issued JENNIFER RABUCHIN
Final 2/23/2026 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 2/23/2026 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 2/23/2026 Corrections Issued JENNIFER RABUCHIN
Service/Power Release 2/23/2026 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/9/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 3/9/2026 Approved JENNIFER RABUCHIN
Final 3/9/2026 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 3/9/2026 Approved JENNIFER RABUCHIN
HVAC-Final 3/9/2026 Approved JENNIFER RABUCHIN
MERV13>=Final 3/9/2026 Approved JENNIFER RABUCHIN
PLUMBING-Final 3/9/2026 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/9/2026 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 3/9/2026 Approved JENNIFER RABUCHIN